ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
LAWA's[1][2][3][4] project page: "Ingress Roadways completion is anticipated in May 2028. Project completion is anticipated mid-2030"; a month takes its last day.
The inbound half of LAX's 4.4-mile roadway rebuild, which separates airport traffic from Sepulveda Boulevard and neighbourhood streets, is due in May 2028, two months before the Games.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Pennrose's[1] May 2028 completion is conditional on funding that had not been awarded in any source found, and a lawsuit seeks to block the land sale; the date is a developer target only.
Planned 60-home senior community on the 1016–1024 North 2nd Street site, with studios and one-bedrooms for adults 55+ earning no more than 60% AMI. Completion targeted for May 2028, contingent on funding.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Pin date 2028-05-31 reflects McShane's May 2028 target; Atlanta Housing[4] says only spring 2028. Both are targets, not an opening.
The Overlook at Garson will add 130 affordable apartments near Lindbergh MARTA and the future Northeast Beltline. McShane expects completion in May 2028; income eligibility ranges from 50% to 80% AMI.
County Road MM, northeast of Hereford, Deaf Smith County, Texas, 79045, United StatesGoogle
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Target commercial operation beginning in 2028 aligned with ERCOT and EIA-860M interconnection queue filings for IP Roman generation and Deaf Smith County Chapter 312 tax abatement milestones.[1]
Google and Intersect Power affiliate IP Roman III Gas are developing Project Roman, a hyperscale data center campus powered by the 1,474 MW gas-fired Roman Energy Center across 3,700 acres in Deaf Smith County, Texas; total capital cost has not been published while county tax abatements anticipate over 108 million USD in PILOT revenue.
Estimated: 22151 NW Service Road, Warrenton, Warren County, Missouri 63383, United States (approximate: Warrenton city centroid used; the street address comes from the city's filing)Crusoe
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Cleanview state-leads planned COD: 2028 (Crusoe Warrenton Building 1).[1]
Crusoe's affiliate Warrenton DC Owner 1 LLC plans two 805,000 sq ft data centers on about 337 acres in Warrenton, Missouri (600 MW across two 300 MW buildings per Cleanview; no MW figure from Crusoe or Ameren), with about 8.37B USD of servers per phase in the city's filing and Meta reportedly contracted for capacity.
Estimated: Google Kansas City East Campus Building 4, NE Parvin Road & Hunt Midwest Corridor, Kansas City, Clay County, MO 64161Google
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Unverified legacy June 2028 COD; county completeness determination is not an approved schedule.[1]
Shawnee County marked Compass’s CU-26-203 application complete September 9,2026, without approving its merits or scheduling a hearing. The applicant’s revised plan gives 400 MW final IT load across ten buildings and roughly 500–600 MW total demand, replacing the 153 MW tracker claim.
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins17 months late55% CONFIDENCEOverall confidence: 55%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
AI Weekly[3] (19 Jul 2026): "targeting first operations by summer 2028"; DCD (12 Jan 2026): IID said "the project could go live as early as January 2027". Both predate the 9 Sep 2026 ruling, so the real date is unknown.
Imperial Valley Computer Manufacturing's 330 MW, roughly 10B USD, 950,000 sq ft campus near the City of Imperial lost its county approval on 9 September 2026 when an Imperial County judge ruled CEQA review was required; the developer plans to seek a new trial and appeal.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Unverified legacy June 2028 COD. Current operator says construction could begin as early as 2028, not operation.[1]
Alcove’s current project page describes Project Catalyst with MDH Partners: 283 acres, up to seven buildings and approximately 3.3 million square feet, scaling toward 500-plus MW. Construction could start as early as 2028 after approvals; that is not an opening date.
Route 6 and Gun Club Road, Morris, Grundy County, Illinois, United StatesTract
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Bisnow[5] (27 Jan 2026): "Initial energization is targeted for June 2028"; Tract's FAQ hosted by the City of Morris: "Initial power delivery to the site is expected in Q2 of 2028". Full 1 GW load ramp by 2032 per Bisnow.
Tract bought a 343-acre zoned site in Morris, Grundy County, Illinois in January 2026 for a campus of up to 1,000 MW (1GW) with ComEd power, initial energization targeted for June 2028; the land cost about 51.5M USD and no project cost has been published.
Estimated: Switch Citadel Campus Building 7, Milan Drive, Tahoe Reno Industrial Center, McCarran, Storey County, NV 89434Switch
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
Wilson County, Texas; retained EIA 67250 rounded reporting point, not a surveyed phase boundaryAdvanced Power
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
June 1 is month-only precision for EIA[2] June 2028; operator publishes year 2028 without an exact day. Neither is COD evidence.
Advanced Power’s current portfolio describes Alina in Wilson County as proposed solar-plus-storage, with a 200 MW / 400 MWh battery, 222 MWdc solar and 2028 target operation. EIA plant 67250 lists separate 200 MW battery and solar generators, with June 2028 target and approvals not initiated.
Sardis-Clarksdale Storage Center, Interstate 55 Corridor, Batesville, Panola County, MS 38606Entergy Mississippi
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Sardis to Clarksdale Clean Energy Storage Center remains an unconfirmed project identity. Its previously reported developer, capacity, investment, construction stage and operating schedule are not substantiated by the cited project material.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Given as a target, not a fixed date, per en.wikipedia.org[1]: "…nnelling commenced in mid 2024, with an expected completion in late 2028.[7][8] In 2021, the length…"
Victoria's largest road project, burying the missing link in Melbourne's ring road in twin three-lane tunnels. Estimated date.
Estimated: QTS Denver Data Center Campus, East 56th Avenue, Aurora, Adams County, CO 80011QTS Data Centers
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.