ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins92% CONFIDENCEOverall confidence: 92%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
The saved calendar date is an estimated development-tracking target, not a verified exact opening. Status follows the quoted planning or actual-work milestone.[1]
The City of Lebanon explicitly reports Meta breaking ground February 11, 2026. Its more-than-USD10bn campus investment supersedes the earlier USD800m first-phase proposal; this is the full announced campus investment, not an equipment-only amount.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins92% CONFIDENCEOverall confidence: 92%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
July 1, 2026 is an unverified legacy tracker timeline anchor, not an operator-published opening day. Stage is supported separately by the cited evidence.[1]
The county-hosted planning market analysis names TPC Data Center MidAtlantic at 6201 Frost Place and explicitly proposes 2027 development. Proposed applies to that named parcel, not a completed data center or nearby Konterra project. The tracker’s 20MW is unverified and removed. Planning floor area and a projected delivery year do not establish commissioning or cost.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins92% CONFIDENCEOverall confidence: 92%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
July 1, 2026 is an unverified legacy tracker timeline anchor, not an operator-published opening day. Stage is supported separately by the cited evidence.[1]
Microsoft’s July 2026 update confirms active grading by Ryan Central at La Porte. In Progress applies before vertical building, not completed operation. Indiana’s June 2024 announcement identifies a planned USD1bn investment for the initial campus; the newer update supplies no revised total. The unverified tracker 100MW and combined later-parcel dimensions are removed.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins92% CONFIDENCEOverall confidence: 92%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
July 1, 2026 is an unverified legacy tracker timeline anchor, not an operator-published opening day. Stage is supported separately by the cited evidence.[1]
The governor explicitly confirms having broken ground on Compass Meridian, and the July 2026 issuer workforce release retains the USD10bn full-campus investment. In Progress applies before full phased delivery, not to an already operating entire campus. The generic tracker 500MW is not independently verified here and is removed. This cost is the digital-infrastructure project, not a separate Mississippi power plant.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins88% CONFIDENCEOverall confidence: 88%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Data Center Tracker boundary verified footprint[1]
Data center campus in Michigan with tracked parcel boundary (1440 acres, 1000 MW).
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins89% CONFIDENCEOverall confidence: 89%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
July 1, 2026 is an unverified legacy tracker timeline anchor, not an operator-published opening day. Stage is supported separately by the cited evidence.[1]
Liberty’s March 24 announcement and municipal FAQ describe a planned three-building data center with projected 150MW demand. Proposed applies to the announced project before verified physical works. The city states USD1.4bn total investment including real and personal property; the components are not added again. This source reconciles the previously different local and production prices.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins88% CONFIDENCEOverall confidence: 88%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Data Center Tracker boundary verified footprint[1]
Data center campus in Iowa with tracked parcel boundary (127 acres, 1,000,000 sq ft, 100 MW).
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins92% CONFIDENCEOverall confidence: 92%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
The saved calendar date is an estimated development-tracking target, not a verified exact opening. Status follows the quoted planning or actual-work milestone.[1]
Clarksdale’s own FAQ describes its proposed hyperscale project. The USD10bn figure in that FAQ refers to the separate Madison County Project Atlas and must not be assigned here.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins92% CONFIDENCEOverall confidence: 92%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
July 1, 2026 is an unverified legacy tracker timeline anchor, not an operator-published opening day. Stage is supported separately by the cited evidence.[1]
Davenport’s FY2025 financial report explicitly says Vemerald is planning a northwest Davenport campus for Meta while negotiating utility service. Proposed applies to that planned campus; later directories do not establish actual works. The generic tracker 100MW is removed. A USD420m assessed-valuation assumption for tax analysis is not construction expenditure, and no precise opening date is established.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins88% CONFIDENCEOverall confidence: 88%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Data Center Tracker boundary verified footprint[1]
Data center campus in Michigan with tracked parcel boundary (412 acres, 1000 MW).
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins88% CONFIDENCEOverall confidence: 88%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Data Center Tracker boundary verified footprint[1]
Data center campus in Iowa with tracked parcel boundary (2000 acres, 100 MW).
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins88% CONFIDENCEOverall confidence: 88%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Data Center Tracker boundary verified footprint[1]
Data center campus in Maryland with tracked parcel boundary (432 acres, 100 MW).