CONFIRMEDDate confidence: CONFIRMEDStated as firmHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all CONFIRMED pins74% CONFIDENCEOverall confidence: 74%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence43 days ago
WCAX[1] (Oct 5, 2026) reports the battery and solar array are online after a celebration with Gov. Phil Scott; the exact energization date is not stated, so the date is the Oct 5, 2026 event report.Lightshift Energy built a 16 MW, up to 52 MWh behind-the-meter battery at GlobalFoundries' Essex Junction, Vermont campus to shave peak demand. WCAX reported on Oct 5, 2026 that the battery and a companion on-site solar array are now online, and GlobalFoundries calls it the largest battery ever installed in Vermont.