Early 2028 electricity generation. WAPDA’s current Mohmand project page targets electricity generation in early 2028. The whole multipurpose-dam investment includes non-power water infrastructure. The timeline uses a year-level marker; it does not claim a specific early-2028 commissioning day.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost.
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost. Mohmand multipurpose dam and hydropower project: 800 MW generating project rating. Operator-reported electric generating capacity; not annual energy production
WAPDA’s current project page identifies 800 MW installed design capacity, ongoing construction, river diversion November 2024, dam impounding targeted late 2026 and electricity generation early 2028. Targets are not completion claims.
WAPDA January 19, 2026 reports construction continuing on ten key sites.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Bearbeitetvon @ThePinGang
Bearbeitetvon @ThePinGang
Vorher
Vorher
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost.
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost. Mohmand multipurpose dam and hydropower project: 800 MW generating project rating. Operator-reported electric generating capacity; not annual energy production
WAPDA’s current project page identifies 800 MW installed design capacity, ongoing construction, river diversion November 2024, dam impounding targeted late 2026 and electricity generation early 2028. Targets are not completion claims.
WAPDA January 19, 2026 reports construction continuing on ten key sites.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Das sind Leserfotos, getrennt von den belegten Medien des Pins.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Veröffentlichtes Ziel: Stromerzeugung Anfang 2028. Der Bau ist dokumentiert, aber dieser künftige Fertigstellungs-/Betriebsmeilenstein ist geschätzt. Das Datum ist eine Zeitleistenmarke auf Jahres-/Monatsende-Ebene und kein bestätigter genauer Eröffnungstag. Quelle: https://wapda.gov.pk[3][4]/mohmand-dam-hydropwer-project/
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost. Mohmand multipurpose dam and hydropower project: 800 MW generating project rating. Operator-reported electric generating capacity; not annual energy production
WAPDA’s[4] current project page identifies 800 MW installed design capacity, ongoing construction, river diversion November 2024, dam impounding targeted late 2026 and electricity generation early 2028. Targets are not completion claims.
WAPDA[3] January 19, 2026 reports construction continuing on ten key sites.
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: Mohmand multipurpose dam and hydropower project — estimated target 2028
Stromerzeugung Anfang 2028. Die aktuelle Mohmand-Projektseite der WAPDA nennt als Ziel die Stromerzeugung Anfang 2028. Die Gesamtinvestition in den Mehrzweck-Staudamm umfasst Wasserinfrastruktur ohne Stromerzeugung. Die Zeitleiste verwendet eine Marke auf Jahresebene; sie behauptet keinen bestimmten Inbetriebnahmetag Anfang 2028.[3]
Der Bau ist verifiziert; das Fertigstellungsdatum bleibt eine Schätzung. Der Zeitstrahl-Marker steht für das veröffentlichte Zieljahr bzw. den Zielmonat, nicht für einen bestätigten Eröffnungstag.
Der Projekteintrag des OPEC Fund nennt Gesamtprojektkosten von 2,249.60 Millionen US-Dollar. Sie umfassen das Mehrzweck-Staudammprogramm, einschließlich Wasserversorgung, Bewässerung und Hochwasserschutz, nicht nur das Kraftwerk. Das Darlehen des Fonds wird nicht als Projektkosten verwendet.[2][3][4]
Der Projekteintrag des OPEC Fund nennt Gesamtprojektkosten von 2,249.60 Millionen US-Dollar. Sie umfassen das Mehrzweck-Staudammprogramm, einschließlich Wasserversorgung, Bewässerung und Hochwasserschutz, nicht nur das Kraftwerk. Das Darlehen des Fonds wird nicht als Projektkosten verwendet. Mehrzweck-Staudamm und Wasserkraftprojekt Mohmand: Nennleistung des Projekts 800 MW. Vom Betreiber gemeldete elektrische Erzeugungskapazität; keine jährliche Energieerzeugung[2]
Die aktuelle Projektseite der WAPDA nennt 800 MW installierte Auslegungsleistung, laufenden Bau, Flussumleitung im November 2024, Einstau des Damms für Ende 2026 und Stromerzeugung Anfang 2028. Ziele sind keine Fertigstellungsbehauptungen.[3]
Die WAPDA meldet am 19. Januar 2026, dass der Bau an zehn Schlüsselstandorten weitergeht.[4]
Berücksichtigt werden nur Projekte mit dokumentierter physischer Bauarbeit, Inbetriebnahme oder Eröffnung 2025–2026 sowie veröffentlichten projektspezifischen Kosten und elektrischer Leistung. Kosten verwenden den veröffentlichten Umfang und die veröffentlichte Währung; es gibt keine Richtwertschätzungen oder Währungsumrechnungen. MW ist Leistungskapazität, nicht jährliche Stromerzeugung. Erwartete Jahresenergie ist, wo angegeben, eine Prognose. Der Kartenpunkt ist ein gemeldeter Standort von Anlage/Projekt und kann ungefähr sein. Übereinstimmende Bestandsansichten und ausgeschlossene Erweiterungsvorschläge sind keine additive Kapazität.
Maschinenhausbauwerk von Mohmand, identifiziert in der Projektgalerie der WAPDA; Aufnahmedatum des Fotos nicht veröffentlicht. Bildnachweis: WAPDA; einzelner Fotograf nicht genannt. Quelle und Galerie; Originalmedium.
Hochwasserentlastung und Hauptdammstandort von Mohmand, identifiziert in der Projektgalerie der WAPDA; Aufnahmedatum des Fotos nicht veröffentlicht. Bildnachweis: WAPDA; einzelner Fotograf nicht genannt. Quelle und Galerie; Originalmedium.