ACWA’s current project page publishes US$2.37 billion project cost for the two-plant complex: Al Shuaibah 1 (600 MWac) and Al Shuaibah 2 (2,060 MWac), totaling 2,660 MWac. One pin covers the combined budget and both built plants; the cost is not duplicated on separate phase pins. Al Shuaibah 1 and 2 solar complex: published generating capacity 2660 MW. 600 + 2,060 MW AC; whole two-plant complex ACWA’s project page lists commercial-operation milestones February 28, 2025 for ASB1 and November 30, 2025 for ASB2. Annual-report online-capacity dates differ; both belong to the recent-opening window.
Provides project identity and map location; cost and current status are evidenced separately.
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
2,060 MW total production capacity at full operational capacity (actual); Al Shuaibah 1 capacity is not stated in this source
“Shuaibah 2 independent photovoltaic solar power plant project, with a total production capacity of 2,060 megawatts, achieving full operational capacity.”
Al Shuaibah 1 certified November 2024; Al Shuaibah 2 phases 1-3 commercial operation February 2025 (actual)
“Al Shuaibah 1 Solar Photovoltaic Project in Saudi Arabia, receipt of the Commercial Operation Certificate from the Saudi Power Procurement Company, for the full project capacity.”
Both plants in commercial operation
“The commencement of commercial operations for the first, second, and third phases of the Shuaibah 2 independent photovoltaic solar power plant project”
Financing agreements signed for Al Shuaibah 1 and 2
“July 2023G: The finalization and signing of the financing agreements with the financing consortium for Al Shuaibah 1 and Al Shuaibah 2 PV projects”
Al Shuaibah 1 receives commercial operation certificate for full capacity
“Commercial Operation Certificate from the Saudi Power Procurement Company, for the full project capacity.”
Al Shuaibah 2 phases 1-3 begin commercial operation
“February 2025G: The commencement of commercial operations for the first, second, and third phases of the Shuaibah 2 independent photovoltaic solar power plant project”
Título original: Al Shuaibah 1 and 2: Two Operating Solar Plants
Al Shuaibah 1 y 2 son plantas solares independientes en la provincia de La Meca. El prospecto de ACWA para 2025 informa la certificación comercial completa del proyecto para la planta 1 en noviembre de 2024 y 2.060 MW de operación completa para la planta 2 en febrero de 2025.[1]
El folleto indica una inversión combinada de 8.300 millones de SAR. De ese presupuesto combinado no se asigna ninguna parte específica de la planta.[1]
Power generation2.66 GW · Combined 600 MW and 2,060 MW operating solar capacity. Separate plant profiles must not duplicate the combined budget. · source