- Start
- Jun 27, 201490% CONFIDENCEfrom the source
Gorona del Viento Hydro-Wind Plant Opens on El Hierro
- Gorona del Viento on El Hierro, Canary Islands, was inaugurated on 27 June 2014 as a wind and pumped-hydro system aimed at self-sufficiency[3]
- Five Enercon E-70 turbines (11.5 MW) pump surplus water to a 380,000 m3 upper reservoir in La Caldera crater, released through four Pelton turbines (11.3 MW) when wind is low[2][3]
- The plant covered 19.2% of demand in 2015, 40.7% in 2016 and 46.5% in 2017, and ran 18 consecutive days on 100% renewables in early 2018[3]
- It has avoided more than about 30,000 tons of CO2 and about 43,000 barrels of oil imports a year[3]
References 380% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]90%youtube.com/watch?v=A9h2pCsevZYyoutube.com· Posted Sep 22, 2026· Starts Jun 27, 2014 ✓· 50% of score
Renewable-energy trade coverage and the plant operator's own materials date the Gorona del Viento[2] inauguration to 27 June 2014.
- [2]70%Gorona del Viento El Hierro, S.A. - official sitegoronadelviento.es· Added Sep 22, 2026· 50% of score
The plant operator's own site confirms the facility and its role in supplying El Hierro's electricity.[1]
- [3]80%Gorona del Viento: The Hydro-Wind Power Plant that Supplies Renewable Energy to El Hierroen.renovablesverdes.com· Published Jun 27, 2014· 0% of score
Renewable-energy trade press dates the Gorona del Viento[2] inauguration to 27 June 2014 and describes the wind-pumped-hydro design.
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.