Chronopin tracks 38 individual Microsoft data centre sites, listed in their pin titles as 24 under construction, 7 planned and 7 operational, across the US, Canada, Europe, Brazil and Australia. Three Danish sites at Gadstrup, Høje Taastrup and Køge are listed as operational [1] [2] [3].
The flagship is Fairwater in Mount Pleasant, Wisconsin, a single cluster of NVIDIA GB200 servers Microsoft calls the world's most powerful AI supercomputer, fully operational on 23 June 2026 after its equipment came online in April [4]. A second Fairwater datacenter beside it is under construction for 2028 with a further 4 billion USD pledged [5]. In San Jose, the California Energy Commission lists a two-building project with a maximum load of 99 MW [6].