Ce pin suit l'actualité : il montre ce que l'on sait maintenant, et voici ce qui a changé et pourquoi.
Modifiépar @ThePinGang
Avant
Phase 2 in 2027. MGEN’s July 8, 2025 project update identifies Phase 1 completion in early 2026 and Phase 2 targeted the following year, 2027. Its September 2026 release separately confirms Phase 1 commercial operation; the whole complex is not described as already fully operating.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
MGEN’s November 2024 groundbreaking release identifies investment above PHP200 billion for 3,500 MWp PV with 4,500 MWh battery storage and related interconnection. This is a published approximate lower-bound project investment, not an enterprise valuation. Generation excludes battery MW/MWh.
MGEN’s November 2024 groundbreaking release identifies investment above PHP200 billion for 3,500 MWp PV with 4,500 MWh battery storage and related interconnection. This is a published approximate lower-bound project investment, not an enterprise valuation. Generation excludes battery MW/MWh. MTerra Solar and battery complex: 3500 MW generating project rating. Full complex design: 3,500 MWp DC solar; Phase 1 contracted firm supply 600 MW AC, not additive
MGEN September 3, 2026 confirms Phase 1 commercial operation for 600 MWac mid-merit supply under its PPA. The entire built complex is still being completed; full 3,500 MWp must not be called currently commercially operating.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Modifiépar @ThePinGang
Modifiépar @ThePinGang
Avant
Avant
MGEN’s November 2024 groundbreaking release identifies investment above PHP200 billion for 3,500 MWp PV with 4,500 MWh battery storage and related interconnection. This is a published approximate lower-bound project investment, not an enterprise valuation. Generation excludes battery MW/MWh.
MGEN’s November 2024 groundbreaking release identifies investment above PHP200 billion for 3,500 MWp PV with 4,500 MWh battery storage and related interconnection. This is a published approximate lower-bound project investment, not an enterprise valuation. Generation excludes battery MW/MWh. MTerra Solar and battery complex: 3500 MW generating project rating. Full complex design: 3,500 MWp DC solar; Phase 1 contracted firm supply 600 MW AC, not additive
MGEN September 3, 2026 confirms Phase 1 commercial operation for 600 MWac mid-merit supply under its PPA. The entire built complex is still being completed; full 3,500 MWp must not be called currently commercially operating.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Photos de lecteurs, distinctes des médias sourcés du pin. Notez ce que vous avez mangé ou vu et, sur un pin de restaurant, identifiez les plats directement sur votre photo.
La première entrée est toujours la source de l’épingle. La confiance globale est une moyenne pondérée de la fermeté avec laquelle chaque référence étaye les heures de début et de fin retenues ci-dessus ; une référence compte moitié moins pour chaque tranche de 180 jours d’ancienneté par rapport à la plus récente.
Objectif publié : phase 2 en 2027. La construction est documentée, mais ce jalon futur d’achèvement/de mise en service est une estimation. La date est un repère de calendrier de fin d’année/de mois et non un jour d’ouverture exact confirmé. Source : https://www.meralcopowergen[2][3][4].com.ph/mterra-solar-becomes-largest-solar-pv-installation-in-ph/
MGEN’s July 8, 2025 project update identifies Phase 1 completion in early 2026 and Phase 2 targeted the following year, 2027. Its September 2026 release separately confirms Phase 1 commercial operation; the whole complex is not described as already fully operating.[1]
MGEN’s November 2024 groundbreaking release identifies investment above PHP200 billion for 3,500 MWp PV with 4,500 MWh battery storage and related interconnection. This is a published approximate lower-bound project investment, not an enterprise valuation. Generation excludes battery MW/MWh. MTerra Solar and battery complex: 3500 MW generating project rating. Full complex design: 3,500 MWp DC solar; Phase 1 contracted firm supply 600 MW AC, not additive[1]
MGEN September 3, 2026 confirms Phase 1 commercial operation for 600 MWac mid-merit supply under its PPA. The entire built complex is still being completed; full 3,500 MWp must not be called currently commercially operating.[1]
Il manque quelque chose ou une erreur s'est glissée ? Dites-le avec vos mots : un lien qui étaye cette épingle, une autre date de début ou de fin et pourquoi, ou une information absente ou erronée. L'IA la vérifie au regard des sources de l'épingle, en cherche de meilleures et ajoute toute page qui vous donne raison. Les sources de l'épingle restent celles qui comptent le plus. L'IA regarde aussi les images : une image qui montre autre chose, ou qui le montre mal, passe en dernier ou est remplacée.
Titre original: MTerra Solar and battery complex — estimated target 2027
Phase 2 en 2027. La mise à jour du projet de MGEN du 8 juillet 2025 indique l’achèvement de la phase 1 début 2026 et la phase 2 prévue l’année suivante, 2027. Son communiqué de septembre 2026 confirme séparément l’exploitation commerciale de la phase 1 ; le complexe entier n’est pas décrit comme déjà pleinement en service.[2]
La construction est vérifiée ; la date d’achèvement reste une estimation. Le repère de la chronologie correspond à l’année/au mois cible publié, et non à un jour d’ouverture confirmé.
Le communiqué de MGEN de novembre 2024 sur le lancement des travaux indique un investissement supérieur à 200 milliards de PHP pour 3,500 MWc de photovoltaïque avec 4,500 MWh de stockage par batteries et l’interconnexion associée. Il s’agit d’un investissement approximatif du projet publié comme borne inférieure, et non d’une valorisation d’entreprise. La production exclut les MW/MWh des batteries.[3][4]
Le communiqué de MGEN de novembre 2024 sur le lancement des travaux indique un investissement supérieur à 200 milliards de PHP pour 3,500 MWc de photovoltaïque avec 4,500 MWh de stockage par batteries et l’interconnexion associée. Il s’agit d’un investissement approximatif du projet publié comme borne inférieure, et non d’une valorisation d’entreprise. La production exclut les MW/MWh des batteries. Complexe MTerra Solar et batteries : puissance nominale de production du projet de 3500 MW. Conception du complexe complet : 3,500 MWc de solaire en courant continu ; fourniture ferme contractée de la phase 1 de 600 MW en courant alternatif, non cumulative[3]
Le 3 septembre 2026, MGEN confirme l’exploitation commerciale de la phase 1, avec 600 MWca de fourniture en semi-base au titre de son contrat d’achat d’électricité. Le complexe construit dans son ensemble est encore en cours d’achèvement ; il ne faut pas affirmer que les 3,500 MWc complets sont actuellement en exploitation commerciale.[4]
Seuls sont retenus les projets dont la construction physique, la mise en service ou l’ouverture en 2025–2026 est documentée, avec des coûts et une puissance électrique publiés propres au projet. Les coûts utilisent le périmètre et la devise publiés ; aucune estimation de référence ni conversion de devise. Le MW est une capacité de puissance, non une production annuelle d’électricité. L’énergie annuelle attendue, lorsqu’elle est indiquée, est une prévision. Le point sur la carte est un emplacement déclaré de la centrale ou du projet et peut être approximatif. Les vues d’inventaire correspondantes et les propositions d’extension exclues ne sont pas des capacités additionnelles.
Image du site MTerra Solar accompagnant l’annonce de l’exploitant de septembre 2026 sur la mise en service de la phase 1 ; le complexe dans son ensemble reste en construction. Crédit : Meralco PowerGen / MTerra Solar ; photographe individuel non nommé. Source et galerie; média original.
Vue du site de la phase 1 de MTerra Solar fournie par Meralco PowerGen, septembre 2026. Crédit : Meralco PowerGen / MTerra Solar ; photographe individuel non nommé. Source et galerie; média original.