Pin ini mengikuti berita: pin ini menampilkan apa yang diketahui saat ini, dan di sini ada apa yang berubah serta penyebabnya.
Dieditoleh @ThePinGang
Sebelumnya
2028. Entergy’s May 19, 2026 update documents HRSG module erection and turbine delivery and retains the Delta Blues opening target in 2028.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
Entergy’s May 19, 2026 update reports HRSG module erection and turbine delivery at Delta Blues, and states 754 MW and $1.2 billion investment. The operator’s physical-work evidence qualifies the project despite the conflicting preliminary inventory status. Service in 2028 remains a target.
Published project-specific cost for Delta Blues Advanced Power Station: USD 1.2e+09. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Delta Blues Advanced Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Entergy’s May 19, 2026 construction update confirms installation of heat-recovery steam-generator modules at Delta Blues in Greenville. The operator describes 754 MW and a 2028 opening target.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Dieditoleh @ThePinGang
Dieditoleh @ThePinGang
Sebelumnya
Sebelumnya
Entergy’s May 19, 2026 update reports HRSG module erection and turbine delivery at Delta Blues, and states 754 MW and $1.2 billion investment. The operator’s physical-work evidence qualifies the project despite the conflicting preliminary inventory status. Service in 2028 remains a target.
Published project-specific cost for Delta Blues Advanced Power Station: USD 1.2e+09. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Delta Blues Advanced Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Entergy’s May 19, 2026 construction update confirms installation of heat-recovery steam-generator modules at Delta Blues in Greenville. The operator describes 754 MW and a 2028 opening target.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Ini foto pembaca, terpisah dari media pin yang bersumber.
Entri pertama selalu merupakan sumber pin. Keyakinan keseluruhan adalah rata-rata tertimbang dari seberapa kuat setiap referensi mendukung waktu mulai dan berakhir yang digunakan di atas; bobot sebuah referensi berkurang setengahnya untuk setiap 180 hari lebih lama dari yang terbaru.
Target yang dipublikasikan: 2028. Konstruksi terdokumentasi, tetapi tonggak penyelesaian/operasi di masa depan ini bersifat perkiraan. Tanggalnya adalah penanda akhir tahun/bulan dan bukan hari pembukaan pasti yang terkonfirmasi. Sumber: https://www.entergy[2].com/blog/delta-blues-reaches-important-milestone-in-construction
Published project-specific cost for Delta Blues Advanced Power Station: USD 1.2e+09. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Delta Blues Advanced Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Entergy’s May 19, 2026 construction update confirms installation of heat-recovery steam-generator modules at Delta Blues in Greenville. The operator describes 754 MW and a 2028 opening target.
Ada yang kurang atau salah? Sampaikan dengan kata-kata Anda sendiri: tautan yang mendukung pin ini, tanggal mulai atau berakhir yang berbeda beserta alasannya, atau fakta yang kurang atau keliru. AI memeriksanya terhadap sumber pin ini, mencari sumber yang lebih baik, dan menambahkan halaman mana pun yang mendukung Anda. Sumber pin itu sendiri tetap paling diperhitungkan. Gambar yang menampilkan hal lain, atau menampilkannya dengan buruk, juga diperiksa, lalu diturunkan atau diganti.
Judul asli: Delta Blues Advanced Power Station — estimated target 2028
2028. Pembaruan Entergy tanggal 19 Mei 2026 mendokumentasikan pemasangan modul HRSG dan pengiriman turbin, serta mempertahankan target pembukaan Delta Blues pada 2028.[2]
Konstruksi telah terverifikasi; tanggal penyelesaian masih berupa perkiraan. Penanda lini masa mewakili tahun/bulan target yang dipublikasikan, bukan hari pembukaan yang terkonfirmasi.
Pembaruan Entergy tanggal 19 Mei 2026 melaporkan pemasangan modul HRSG dan pengiriman turbin di Delta Blues, serta menyebut 754 MW dan investasi 1,2 miliar USD. Bukti pekerjaan fisik operator menjadikan proyek ini memenuhi syarat meski status dalam inventaris awal saling bertentangan. Layanan pada 2028 tetap berupa target.[2]
Biaya khusus proyek yang dipublikasikan untuk Delta Blues Advanced Power Station: USD 1.2e+09. Dasar: perkiraan modal/konstruksi khusus proyek yang dipublikasikan. Peringkat proyek pembangkit listrik yang dipublikasikan untuk Delta Blues Advanced Power Station: 754 MW. Dasar: kapasitas pembangkitan listrik yang dilaporkan operator; bukan produksi energi tahunan. Pembaruan konstruksi Entergy tanggal 19 Mei 2026 mengonfirmasi pemasangan modul generator uap pemulihan panas di Delta Blues di Greenville. Operator menyebut 754 MW dan target pembukaan pada 2028.[2]
Hanya proyek dengan konstruksi fisik, komisioning, atau pembukaan 2025–2026 yang terdokumentasi serta biaya dan keluaran listrik khusus proyek yang dipublikasikan yang dipertahankan. Biaya memakai cakupan dan mata uang yang dipublikasikan; tidak ada perkiraan tolok ukur atau konversi mata uang. MW adalah kapasitas daya, bukan produksi listrik tahunan. Energi tahunan yang diharapkan, bila ada, merupakan perkiraan. Titik peta adalah lokasi pembangkit/proyek yang dilaporkan dan dapat berupa perkiraan. Tampilan inventaris yang cocok dan usulan perluasan yang dikecualikan bukan kapasitas yang dapat dijumlahkan.
Konstruksi Delta Blues: tonggak generator uap pemulihan panas, dipublikasikan pada Mei 2026. Kredit: Entergy Mississippi; fotografer tidak disebutkan. Sumber dan galeri; media asli.
Pekerjaan konstruksi Delta Blues dari galeri tonggak operator Mei 2026. Kredit: Entergy Mississippi; fotografer tidak disebutkan. Sumber dan galeri; media asli.
Pengangkutan komponen proyek Delta Blues, dari galeri konstruksi Entergy Mississippi Mei 2026. Kredit: Entergy Mississippi; fotografer tidak disebutkan. Sumber dan galeri; media asli.