Pin ini mengikuti berita: pin ini menampilkan apa yang diketahui saat ini, dan di sini ada apa yang berubah serta penyebabnya.
Dieditoleh @ThePinGang
Sebelumnya
End of 2027. TVA’s FY2025 filing identifies physical construction of the 1,500 MW Kingston combined-cycle replacement plant and expected operation by the end of calendar 2027.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Dieditoleh @ThePinGang
Dieditoleh @ThePinGang
Sebelumnya
Sebelumnya
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Ini foto pembaca, terpisah dari media pin yang bersumber.
Entri pertama selalu merupakan sumber pin. Keyakinan keseluruhan adalah rata-rata tertimbang dari seberapa kuat setiap referensi mendukung waktu mulai dan berakhir yang digunakan di atas; bobot sebuah referensi berkurang setengahnya untuk setiap 180 hari lebih lama dari yang terbaru.
Target yang dipublikasikan: akhir 2027. Konstruksi terdokumentasi, tetapi tonggak penyelesaian/operasi di masa depan ini bersifat perkiraan. Tanggalnya adalah penanda akhir tahun/bulan dan bukan hari pembukaan pasti yang terkonfirmasi. Sumber: https://www.sec[3].gov/Archives/edgar/data/1376986/000137698625000056/tve-20250930.htm
Kingston Energy Complex site construction, published March 6, 2025 alongside a TVA construction announcement. The image covers the wider energy complex, including the combined-cycle and aeroderivative work; it is not a photograph of a completed replacement plant.[1]
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.[1]
Ada yang kurang atau salah? Sampaikan dengan kata-kata Anda sendiri: tautan yang mendukung pin ini, tanggal mulai atau berakhir yang berbeda beserta alasannya, atau fakta yang kurang atau keliru. AI memeriksanya terhadap sumber pin ini, mencari sumber yang lebih baik, dan menambahkan halaman mana pun yang mendukung Anda. Sumber pin itu sendiri tetap paling diperhitungkan. Gambar yang menampilkan hal lain, atau menampilkannya dengan buruk, juga diperiksa, lalu diturunkan atau diganti.
Judul asli: Kingston combined-cycle replacement plant — estimated target 2027
Akhir 2027. Pengajuan tahun fiskal 2025 TVA mengidentifikasi konstruksi fisik pembangkit pengganti siklus gabungan Kingston 1.500 MW dan mengharapkan operasi pada akhir tahun kalender 2027.[3]
Konstruksi telah terverifikasi; tanggal penyelesaian masih berupa perkiraan. Penanda lini masa mewakili tahun/bulan target yang dipublikasikan, bukan hari pembukaan yang terkonfirmasi.
Formulir 10-K tahun fiskal 2025 TVA memublikasikan 1,8 miliar dolar telah dibelanjakan dan 1,1 miliar dolar belanja tambahan yang diharapkan untuk pembangkit siklus gabungan Kingston 1.500 MW, per 30 September 2025. Jumlahnya sekitar 2,9 miliar dolar. Total ini adalah aritmetika atas jumlah proyek yang diungkapkan, bukan perkiraan tolok ukur. RFP baterai, ekspansi yang diusulkan, dan peringkat kampus yang lebih luas tidak termasuk.[3]
Formulir 10-K tahun fiskal 2025 TVA memublikasikan 1,8 miliar dolar telah dibelanjakan dan 1,1 miliar dolar belanja tambahan yang diharapkan untuk pembangkit siklus gabungan Kingston 1.500 MW, per 30 September 2025. Jumlahnya sekitar 2,9 miliar dolar. Total ini adalah aritmetika atas jumlah proyek yang diungkapkan, bukan perkiraan tolok ukur. RFP baterai, ekspansi yang diusulkan, dan peringkat kampus yang lebih luas tidak termasuk. Kapasitas pembangkitan yang dipublikasikan untuk pembangkit pengganti siklus gabungan Kingston: 1500 MW. Kapasitas pembangkitan listrik yang dilaporkan operator; bukan produksi energi tahunan. TVA secara eksplisit menyatakan sedang membangun pembangkit siklus gabungan 1.500 MW dengan target akhir 2027. Kapasitas ini untuk pembangkit siklus gabungan, bukan semua unit di lokasi Kingston.[3]
Hanya proyek dengan konstruksi fisik, komisioning, atau pembukaan 2025–2026 yang terdokumentasi serta biaya dan keluaran listrik khusus proyek yang dipublikasikan yang dipertahankan. Biaya memakai cakupan dan mata uang yang dipublikasikan; tidak ada perkiraan tolok ukur atau konversi mata uang. MW adalah kapasitas daya, bukan produksi listrik tahunan. Energi tahunan yang diharapkan, bila ada, merupakan perkiraan. Titik peta adalah lokasi pembangkit/proyek yang dilaporkan dan dapat berupa perkiraan. Tampilan inventaris yang cocok dan usulan perluasan yang dikecualikan bukan kapasitas yang dapat dijumlahkan.
Konstruksi lokasi Kingston Energy Complex, dipublikasikan pada 6 Maret 2025 bersama pengumuman konstruksi TVA. Gambar ini mencakup kompleks energi yang lebih luas, termasuk pekerjaan siklus gabungan dan aeroderivatif; ini bukan foto pembangkit pengganti yang telah selesai. Kredit: pengumuman Tennessee Valley Authority melalui 3B Media News; fotografer tidak teridentifikasi. Sumber dan galeri; media asli.