La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
La data salvata è un indicatore di tracciamento stimato o di traiettoria di capacità, non un giorno di apertura esatto verificato. Lo stato di costruzione segue l'ambito fisico datato citato; nessun completamento viene dedotto dagli obiettivi trascorsi.
Construction research 2026-10-24: Epoch’s[1] 2026-07-05 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Construction equipment present all around site.” Dated observation 2026-07-05; future trajectory rows and modeled costs are distinguished from this physical milestone.
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
| 2026-07-05 |
|---|
| Il raffreddamento dell'edificio 1 sembra completato. L'installazione del generatore di backup continua adiacente a B1. L'installazione del raffreddamento dell'edificio 2 continua. Sono presenti piast… |
| 2026-12-31 | Riteniamo che gli edifici 1 e 2 saranno pienamente operativi entro la fine del secondo semestre del 2026 |
|---|
Note sulle immagini satellitari di Epoch AI, in ordine di data. · fonte
Physical-stage observation dated 2026-07-05. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Construction equipment present all around site.”
Epoch’s dated 2026-07-05 assessment: Construction equipment present all around site. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Construction equipment present all around site.”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing and site prep begins at least as early as July 2023.
“Land clearing and site prep begins at least as early as July 2023.”
Epoch assessment: Building 1 cooling looks complete.
“Building 1 cooling looks complete.”
Titolo originale: Microsoft Narvik Norway AI Data Center Buildout
Microsoft Narvik Norvegia a Bjerkvik, Narvik, Norvegia è un campus di data center AI di frontiera gestito da Nscale/Microsoft che raggiunge 92 MW di capacità di potenza e 265.285 acceleratori AI equivalenti a H100. Il campus del data center utilizzerà l’energia idroelettrica locale con costi elettrici compresi tra 4 e 5 centesimi per unità rispetto a 10 centesimi in altre parti d’Europa.
L'osservazione di Epoch del 05-07-2026 documenta la restante costruzione/installazione fisica per questo edificio denominato. In Progress non completa gli edifici operativi precedenti o la capacità futura. I conteggi di potenza e acceleratore rimangono stime epocali, non una valutazione certificata dall'operatore. I costi di capitale modellati in dollari del 2025 includono l'hardware di elaborazione e non rappresentano un budget di costruzione nativo della fonte.