La prima voce è sempre la fonte del pin. L’affidabilità complessiva è una media ponderata di quanto ogni fonte conferma gli orari di inizio e fine indicati sopra; una fonte conta la metà per ogni 180 giorni in più rispetto alla più recente.
Start è il disboscamento del territorio osservato via satellite da Epoch[3][7]; Crusoe afferma che la costruzione è iniziata a giugno 2024. La fine è la stima di Epoch per il funzionamento degli edifici 7-8 a novembre 2026; non viene pubblicata alcuna data dello sviluppatore.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][7] 2026-07-28 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “not yet confirmed operational” Dated observation 2026-07-28; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
| 2025-06-28 | L'edificio 1 sembra prossimo al completamento della costruzione, con i refrigeratori installati. OpenAI [ha dichiarato](https://openai.com/index/five-new-stargate-sites/) che "Oracle ha iniziato a fo… |
|---|
| 2025-09-26 | L'edificio 1 è pienamente operativo intorno a questa data. La prima fase è stata "dal vivo" il 30 settembre secondo un [annuncio] di Crusoe (https://www.crusoe.ai/resources/newsroom/crusoe-announces-… |
|---|
| 2025-12-24 | L'edificio 2 è pienamente operativo. Questa data esatta corrisponde alla data di completamento prevista di "Quattro (4) sale dati e un edificio per uffici amministrativi" secondo un [deposito TDLR](h… |
|---|
| 2026-01-15 | La sottostazione da 1 GW sembra prossima al completamento. Sembra che nell'edificio 3 siano installate tutte le apparecchiature di alimentazione e raffreddamento, ma ci sono ancora segni di lavori di… |
|---|
| 2026-03-24 | Gli edifici 3 e 4 sembrano completi, ma non sono pienamente operativi. Accanto non sono parcheggiate così tante auto come nell'Edificio 1-2, il che suggerisce che potrebbero essere ancora in fase di… |
|---|
| 2026-05-23 | Si stima che gli edifici 3 e 4 siano operativi. Il 22 aprile, Oracle [ha pubblicato](https://x.com/i/status/2047012589302153558) che "Ad Abilene, 200 MW sono già operativi". Ciò suggerisce che lì |
|---|
| 2026-07-28 | Gli edifici 5-8 sono strutturalmente completi e coperti ma non ancora confermati operativi (allestimento in corso). La sottostazione sembra completa. |
|---|
| 2026-09-10 | Gli edifici 5-6 sono operativi. Nella conferenza sugli utili del primo trimestre dell'anno fiscale 27 di Oracle (10 settembre 2026), Clay Magouyrk ha affermato che "6 degli 8 edifici del campus, che… |
|---|
| 2026-11-01 | Si stima che gli edifici 7-8 siano operativi. Il 24 marzo, l'Edificio 8 assomigliava più o meno a dove si trovava l'Edificio 3 a settembre. Si stima che l'edificio 3 sarà operativo ad aprile, 7 mesi… |
|---|
Note sulle immagini satellitari di Epoch AI, in ordine di data. · fonte
About 4 million sq ft, eight buildings
“bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
875 acres
“sits Stargate — an 875-acre AI data center campus”
618 MW delivered of 824 MW IT projected (Epoch); campus 1.2 GW grid-level design
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Six of eight buildings delivered; Buildings 7-8 fit-out
“Buildings 5-6 are operational.”
Land clearing begins for Buildings 1-2 (Epoch satellite observation)
“Land clearing begins for northern two buildings (Building 1-2)”
City council approves 85%, 10-year tax abatements
“The Abilene City Council approved 85 percent, 10-year property tax abatements for the site in February 2025”
Second phase of six more buildings announced (eight total, 1.2 GW)
“announced a second phase of six more buildings, bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
$15 billion Crusoe/Blue Owl/Primary Digital joint venture announced for the campus
“On May 21, 2025, Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced the second phase of a $15 billion joint venture to fund the campus.”
Buildings 1-2 live on Oracle Cloud Infrastructure
“Crusoe said on Sept. 30, 2025, that the first phase was running on Oracle Cloud Infrastructure”
Crusoe tops out the eighth and final building
“Crusoe has marked a major milestone in its AI infrastructure expansion by topping out the eighth and final building”
Building 2 fully operational (Epoch estimate; matches TDLR completion date)
“Building 2 is fully operational.”
OpenAI and Oracle drop plan to expand Abilene beyond about 1.2 GW
“OpenAI had planned to expand this site to 2.1 GW, but recently reversed course”
Buildings 5-8 structurally complete and roofed; fit-out ongoing
“Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing).”
Oracle: six of eight buildings, 618 MW, delivered
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Buildings 7-8 estimated operational (full campus; Oracle gave no date)
“Buildings 7-8 are estimated to be operational.”
Manca qualcosa o c’è un errore? Dillo con parole tue: un link che conferma questo pin, una data di inizio o fine diversa e perché, o un fatto che manca o è sbagliato. L’IA lo confronta con le fonti del pin, ne cerca di migliori e aggiunge qualsiasi pagina ti dia ragione. Le fonti del pin contano comunque di più. Anche un’immagine che mostra altro, o lo mostra male, viene esaminata e spostata in basso o sostituita.
Titolo originale: OpenAI Stargate Abilene AI Data Center Buildout
Il campus Stargate di OpenAI ad Abilene, in Texas, è lo sviluppo di otto edifici di Crusoe, circa 4 milioni di piedi quadrati e 1,2 GW, affittato a Oracle. La costruzione è iniziata nel 2024; Oracle ha riferito che sei degli otto edifici sono stati consegnati il 10 settembre 2026, con gli ultimi due ancora in fase di allestimento. Una joint venture da 15 miliardi di dollari finanzia il campus. Epoch AI stima 618 MW di potenza IT attualmente e 824 MW una volta completato.
L'osservazione di Epoch del 28-07-2026 documenta la restante costruzione/installazione fisica per questo edificio denominato. In Progress non completa gli edifici operativi precedenti o la capacità futura. I conteggi di potenza e acceleratore rimangono stime epocali, non una valutazione certificata dall'operatore. I costi di capitale modellati in dollari del 2025 includono l'hardware di elaborazione e non rappresentano un budget di costruzione nativo della fonte.
Campus di formazione e inferenza sull'intelligenza artificiale di frontiera su vasta scala monitorato da Epoch AI con impronte satellitari annotate (70 parti fisiche).