이 핀은 뉴스를 계속 추적합니다. 현재까지 알려진 내용을 보여주며, 무엇이 바뀌었고 그 계기가 무엇인지 여기에 표시합니다.
수정됨@ThePinGang님이
변경 전
Unit 1 in 2030; Unit 2 later. EDF’s February 20, 2026 presentation organises Hinkley Unit 1 for operation in 2030 and Unit 2 twelve months later. The 3.3 GW capacity and GBP35 billion estimate in 2015 sterling cover both reactors; neither is represented as wholly delivered by 2030.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
This is a first-reactor milestone and is excluded from the 12-project full-completion count. Whole-project costs and both-reactor capacity are not allocated to Unit 1.
EDF’s February 20, 2026 results presentation labels Hinkley Point C as a 3.3 GW EPR project and estimates completion cost at £35 billion in 2015 sterling. A 12-month delay could add around £1 billion in the same price basis. Both reactors have documented construction progress; Unit 1 is organized for 2030, with Unit 2 twelve months later. This is actual construction, not an announcement-only proposal.
Published project-specific cost for Hinkley Point C: GBP 3.5e+10. Basis: Completion estimate in constant 2015 GBP; not nominal 2026 GBP. Published electric generating project rating for Hinkley Point C: 3300 MW. Basis: EDF presentation rounded electric project rating: 3.3 GW.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
수정됨@ThePinGang님이
수정됨@ThePinGang님이
변경 전
변경 전
EDF’s February 20, 2026 results presentation labels Hinkley Point C as a 3.3 GW EPR project and estimates completion cost at £35 billion in 2015 sterling. A 12-month delay could add around £1 billion in the same price basis. Both reactors have documented construction progress; Unit 1 is organized for 2030, with Unit 2 twelve months later. This is actual construction, not an announcement-only proposal.
Published project-specific cost for Hinkley Point C: GBP 3.5e+10. Basis: Completion estimate in constant 2015 GBP; not nominal 2026 GBP. Published electric generating project rating for Hinkley Point C: 3300 MW. Basis: EDF presentation rounded electric project rating: 3.3 GW.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
수정됨@ThePinGang님이
변경 전
변경 전
GEM August 2026 snapshot: under construction. 3440 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Additional source view; compare phase coverage and rating conventions before combining figures.
수정됨@ThePinGang님이
변경 전
GEM August 2026 snapshot: under construction. 3440 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
수정됨@ThePinGang님이
변경 전
독자 사진으로, 출처가 있는 핀 미디어와 따로 표시됩니다.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
공표된 목표: 1호기는 2030년, 2호기는 그 이후입니다. 건설은 확인되었지만 이 미래의 완공·가동 이정표는 추정치입니다. 이 날짜는 연도/월말 기준의 타임라인 표시이며 확정된 정확한 개통일이 아닙니다. 출처: https://www.edf[3].fr/sites/groupe/files/2026-02/annual-results-edf-2025-presentation-2026-02-20.pdf
The reactor makes its way into the second reactor building.[1]
Published project-specific cost for Hinkley Point C: GBP 3.5e+10. Basis: Completion estimate in constant 2015 GBP; not nominal 2026 GBP. Published electric generating project rating for Hinkley Point C: 3300 MW. Basis: EDF presentation rounded electric project rating: 3.3 GW.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: Hinkley Point C — first reactor target 2030
1호기는 2030년, 2호기는 그 이후. EDF의 2026년 2월 20일 발표 자료는 힝클리 1호기를 2030년에, 2호기를 12개월 뒤에 가동하는 것으로 계획하고 있습니다. 3.3 GW 용량과 2015년 파운드 기준 350억 파운드 추정치는 두 원자로를 모두 포함하며, 어느 쪽도 2030년까지 전부 완료되는 것으로 제시되지 않습니다.[3]
건설은 확인되었으나 완공일은 여전히 추정치입니다. 타임라인 표시는 공표된 목표 연도/월을 나타내며 확정된 개통일이 아닙니다.
이는 첫 번째 원자로의 이정표이며 전체 완공 12개 사업 집계에서 제외됩니다. 전체 사업 비용과 두 원자로의 용량은 1호기에 배분되지 않습니다.
EDF의 2026년 2월 20일 실적 발표 자료는 힝클리 포인트 C를 3.3 GW 규모의 EPR 사업으로 분류하고 완공 비용을 2015년 파운드 기준 350억 파운드로 추정합니다. 12개월 지연되면 같은 가격 기준으로 약 10억 파운드가 더 들 수 있습니다. 두 원자로 모두 건설 진행이 확인되며, 1호기는 2030년, 2호기는 12개월 뒤로 계획되어 있습니다. 이는 발표 단계의 제안이 아니라 실제 건설입니다.[3]
Hinkley Point C에 대해 공표된 사업별 비용: GBP 3.5e+10. 기준: 완공 시 추정치이며 2015년 불변 파운드 기준입니다. 2026년 명목 파운드가 아닙니다. Hinkley Point C에 대해 공표된 사업별 발전 전기 출력: 3300 MW. 기준: EDF 발표 자료의 반올림된 전기 출력 정격: 3.3 GW.[3]
실제 건설, 시운전 또는 2025–2026년 개통이 확인되고 사업별 비용과 전기 출력이 공표된 사업만 포함합니다. 비용은 공표된 범위와 통화를 사용하며 기준 추정치나 환율 환산은 쓰지 않습니다. MW는 출력 용량이며 연간 전력 생산량이 아닙니다. 예상 연간 에너지가 제시된 경우 이는 예측치입니다. 지도의 점은 보고된 발전소/사업 위치이며 대략적일 수 있습니다. 일치하는 인벤토리 보기와 제외된 확장 제안은 합산할 수 있는 용량이 아닙니다.
원자로가 두 번째 원자로 건물로 들어가고 있습니다. 크레딧: EDF / Hinkley Point C media team. 출처 및 갤러리; 원본 미디어.
세계 최대 크레인 '빅 칼(Big Carl)'이 두 번째 원자로 건물 위에 돔을 들어 올렸습니다. 크레딧: EDF / Hinkley Point C media team. 출처 및 갤러리; 원본 미디어.