이 핀은 뉴스를 계속 추적합니다. 현재까지 알려진 내용을 보여주며, 무엇이 바뀌었고 그 계기가 무엇인지 여기에 표시합니다.
수정됨@ThePinGang님이
변경 전
2027. The current operator project page identifies construction underway and expected customer supply in 2027.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Operator source page; original image.
수정됨@ThePinGang님이
수정됨@ThePinGang님이
변경 전
변경 전
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Operator source page; original image.
수정됨@ThePinGang님이
변경 전
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
수정됨@ThePinGang님이
변경 전
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
수정됨@ThePinGang님이
변경 전
변경 전
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels.
EIA August 2026 generator inventory, plant ID 1364: Mill Creek (KY), Jefferson County, KY. Included 1 new/recent generating units with a summed nameplate rating of 740 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
독자 사진으로, 출처가 있는 핀 미디어와 따로 표시됩니다.
첫 번째 항목은 항상 핀의 출처입니다. 전체 신뢰도는 각 자료가 위의 시작·종료 시각을 얼마나 확실히 뒷받침하는지에 대한 가중 평균이며, 자료는 최신 자료보다 180일 오래될 때마다 가중치가 절반이 됩니다.
공표된 목표: 2027. 건설은 확인되었지만, 이 향후 준공/가동 시점은 추정치입니다. 이 날짜는 연말/월말의 타임라인 표시일 뿐 확정된 개장일이 아닙니다. 출처: https://lge-ku.com[2][3]/mc5
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.[1]
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s[1] August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
빠지거나 잘못된 점이 있나요? 이 핀을 뒷받침하는 링크, 다른 시작일이나 종료일과 그 이유, 빠지거나 잘못된 사실을 자신의 말로 알려주세요. AI가 이 핀의 출처와 대조하고 더 나은 자료를 찾아, 뒷받침하는 페이지를 추가합니다. 핀 자체의 출처가 여전히 가장 중요하게 반영됩니다. AI는 이미지도 확인합니다. 다른 것을 보여주거나 제대로 보여주지 못하는 이미지는 뒤로 옮기거나 교체합니다.
원본 제목: Mill Creek 5 — estimated target 2027
2027년. 사업자의 현재 프로젝트 페이지는 건설이 진행 중이며 2027년에 고객에게 전력을 공급할 예정이라고 밝히고 있습니다.[2]
건설은 확인되었으나 완공일은 여전히 추정치입니다. 타임라인 표시는 공표된 목표 연도/월을 나타내며 확정된 개통일이 아닙니다.
LG&E/KU의 현재 Mill Creek 5 페이지는 정격 용량 645 MW, 비용 9.02억 달러, 건설 진행 중, 2027년 준공 예상을 밝히고 있습니다. 2024년 착공 보도자료에는 640 MW로 기재되었으나, 주요 출력 정격에는 현재 페이지를 사용합니다. EIA의 별도 수치인 740 MW는 추가 발전 용량이 아닌 설비 목록상의 참고 정보로 유지합니다.[2][3]
Mill Creek 5의 공표된 프로젝트별 비용: USD 9.02e+08. 근거: 공표된 프로젝트별 자본/건설비 추정치. Mill Creek 5의 공표된 발전 프로젝트 정격 용량: 645 MW. 근거: 사업자 현재 페이지: 정격 용량 645 MW.[2]
LG&E와 KU는 2024년 11월 13일 Mill Creek 5 착공식을 열었으며, 2027년 가동 예정인 640 MW 규모의 천연가스 복합화력 설비라고 설명합니다. EIA의 2026년 8월 건설 기록도 공사가 진행 중임을 독립적으로 뒷받침합니다. 사업자의 프로젝트 용량 640 MW와 EIA의 발전기 정격 용량은 서로 다른 수치를 사용하므로 두 표기를 모두 유지합니다. 2024년 11월 13일 착공식은 실제 건설을 입증합니다.[3]
실제 건설, 시운전 또는 2025–2026년 개통이 확인되고 사업별 비용과 전기 출력이 공표된 사업만 포함합니다. 비용은 공표된 범위와 통화를 사용하며 기준 추정치나 환율 환산은 쓰지 않습니다. MW는 출력 용량이며 연간 전력 생산량이 아닙니다. 예상 연간 에너지가 제시된 경우 이는 예측치입니다. 지도의 점은 보고된 발전소/사업 위치이며 대략적일 수 있습니다. 일치하는 인벤토리 보기와 제외된 확장 제안은 합산할 수 있는 용량이 아닙니다.
사업자가 제공한 Mill Creek 5 렌더링. 계획된 설비를 보여 주는 일러스트이며, 준공된 발전소의 사진이 아닙니다. 출처 표기: LG&E and KU; 출처 페이지에 작가 미표기. 출처 페이지; 사업자 원본 이미지.
사업자 보도자료에 게시된 2024년 11월 13일 Mill Creek 5 착공식. 출처 표기: LG&E and KU; 출처 페이지에 촬영자 미표기. 출처 페이지; 사업자 원본 이미지.
사업자가 제공한 Mill Creek 5 렌더링. 계획된 설비를 보여 주는 일러스트이며, 준공된 발전소의 사진이 아닙니다. 출처 표기: LG&E and KU; 출처 페이지에 작가 미표기. 사업자 출처 페이지; 원본 이미지.
사업자 보도자료에 게시된 2024년 11월 13일 Mill Creek 5 착공식. 출처 표기: LG&E and KU; 출처 페이지에 촬영자 미표기. 사업자 출처 페이지; 원본 이미지.
LG&E와 KU의 프로젝트 갤러리에서 가져온 Mill Creek 5 건설 현장. 촬영 날짜는 별도로 명시되어 있지 않습니다. 출처 표기: LG&E and KU; 촬영자 미표기. 출처 및 갤러리; 원본 미디어.
LG&E와 KU의 프로젝트 갤러리에서 가져온 Mill Creek 5 건설 현장. 촬영 날짜는 별도로 명시되어 있지 않습니다. 출처 표기: LG&E and KU; 촬영자 미표기. 출처 및 갤러리; 원본 미디어.