2028. Entergy’s May 19, 2026 update documents HRSG module erection and turbine delivery and retains the Delta Blues opening target in 2028.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
Entergy’s May 19, 2026 update reports HRSG module erection and turbine delivery at Delta Blues, and states 754 MW and $1.2 billion investment. The operator’s physical-work evidence qualifies the project despite the conflicting preliminary inventory status. Service in 2028 remains a target.
Published project-specific cost for Delta Blues Advanced Power Station: USD 1.2e+09. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Delta Blues Advanced Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Entergy’s May 19, 2026 construction update confirms installation of heat-recovery steam-generator modules at Delta Blues in Greenville. The operator describes 754 MW and a 2028 opening target.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Disuntingoleh @ThePinGang
Disuntingoleh @ThePinGang
Sebelum
Sebelum
Entergy’s May 19, 2026 update reports HRSG module erection and turbine delivery at Delta Blues, and states 754 MW and $1.2 billion investment. The operator’s physical-work evidence qualifies the project despite the conflicting preliminary inventory status. Service in 2028 remains a target.
Published project-specific cost for Delta Blues Advanced Power Station: USD 1.2e+09. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Delta Blues Advanced Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Entergy’s May 19, 2026 construction update confirms installation of heat-recovery steam-generator modules at Delta Blues in Greenville. The operator describes 754 MW and a 2028 opening target.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Ini foto pembaca, diasingkan daripada media pin yang bersumber.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Sasaran yang diterbitkan: 2028. Pembinaan telah didokumenkan, tetapi pencapaian penyiapan/operasi pada masa hadapan ini adalah anggaran. Tarikh itu ialah penanda garis masa hujung tahun/bulan dan bukan hari pembukaan tepat yang disahkan. Sumber: https://www.entergy[2].com/blog/delta-blues-reaches-important-milestone-in-construction
Published project-specific cost for Delta Blues Advanced Power Station: USD 1.2e+09. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Delta Blues Advanced Power Station: 754 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Entergy’s May 19, 2026 construction update confirms installation of heat-recovery steam-generator modules at Delta Blues in Greenville. The operator describes 754 MW and a 2028 opening target.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: Delta Blues Advanced Power Station — estimated target 2028
2028. Kemas kini Entergy pada 19 Mei 2026 mendokumenkan pemasangan modul HRSG dan penghantaran turbin, serta mengekalkan sasaran pembukaan Delta Blues pada 2028.[2]
Pembinaan telah disahkan; tarikh siap masih anggaran. Penanda garis masa mewakili tahun/bulan sasaran yang diterbitkan, bukan hari pembukaan yang disahkan.
Kemas kini Entergy pada 19 Mei 2026 melaporkan pemasangan modul HRSG dan penghantaran turbin di Delta Blues, serta menyatakan 754 MW dan pelaburan 1.2 bilion USD. Bukti kerja fizikal pengendali melayakkan projek ini walaupun status inventori awal bercanggah. Perkhidmatan pada 2028 kekal sebagai sasaran.[2]
Kos khusus projek yang diterbitkan untuk Delta Blues Advanced Power Station: USD 1.2e+09. Asas: anggaran modal/pembinaan khusus projek yang diterbitkan. Kadaran projek penjanaan elektrik yang diterbitkan untuk Delta Blues Advanced Power Station: 754 MW. Asas: kapasiti penjanaan elektrik yang dilaporkan pengendali; bukan pengeluaran tenaga tahunan. Kemas kini pembinaan Entergy pada 19 Mei 2026 mengesahkan pemasangan modul penjana stim pemulihan haba di Delta Blues di Greenville. Pengendali menyatakan 754 MW dan sasaran pembukaan pada 2028.[2]
Hanya projek dengan pembinaan fizikal, pentauliahan atau pembukaan 2025–2026 yang didokumenkan serta kos dan keluaran elektrik khusus projek yang diterbitkan dikekalkan. Kos menggunakan skop dan mata wang yang diterbitkan; tiada anggaran penanda aras atau penukaran mata wang. MW ialah kapasiti kuasa, bukan pengeluaran elektrik tahunan. Tenaga tahunan yang dijangka, jika diberikan, ialah ramalan. Titik peta ialah lokasi loji/projek yang dilaporkan dan mungkin anggaran. Paparan inventori yang sepadan dan cadangan pengembangan yang dikecualikan bukan kapasiti tambahan.
Pembinaan Delta Blues: pencapaian penjana stim pemulihan haba, diterbitkan pada Mei 2026. Kredit: Entergy Mississippi; jurugambar tidak dinamakan. Sumber dan galeri; media asal.
Kerja pembinaan Delta Blues daripada galeri pencapaian pengendali pada Mei 2026. Kredit: Entergy Mississippi; jurugambar tidak dinamakan. Sumber dan galeri; media asal.
Pengangkutan komponen projek Delta Blues, daripada galeri pembinaan Entergy Mississippi pada Mei 2026. Kredit: Entergy Mississippi; jurugambar tidak dinamakan. Sumber dan galeri; media asal.