Pin ini mengikuti berita: ia menunjukkan apa yang diketahui sekarang, dan inilah apa yang berubah serta apa yang menyebabkannya.
Disuntingoleh @ThePinGang
Sebelum
End of 2027. TVA’s FY2025 filing identifies physical construction of the 1,500 MW Kingston combined-cycle replacement plant and expected operation by the end of calendar 2027.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Disuntingoleh @ThePinGang
Disuntingoleh @ThePinGang
Sebelum
Sebelum
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Foto daripada pembaca, berasingan daripada media bersumber pin. Nilaikan apa yang anda makan atau lihat, dan pada pin restoran, tag hidangan terus pada foto anda.
Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Sasaran yang diterbitkan: akhir 2027. Pembinaan telah didokumenkan, tetapi pencapaian penyiapan/operasi pada masa hadapan ini adalah anggaran. Tarikh itu ialah penanda garis masa hujung tahun/bulan dan bukan hari pembukaan tepat yang disahkan. Sumber: https://www.sec[3].gov/Archives/edgar/data/1376986/000137698625000056/tve-20250930.htm
Kingston Energy Complex site construction, published March 6, 2025 alongside a TVA construction announcement. The image covers the wider energy complex, including the combined-cycle and aeroderivative work; it is not a photograph of a completed replacement plant.[1]
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.[1]
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Tajuk asal: Kingston combined-cycle replacement plant — estimated target 2027
Akhir 2027. Pemfailan tahun fiskal 2025 TVA mengenal pasti pembinaan fizikal loji ganti kitar gabungan Kingston 1,500 MW dan menjangkakan operasi menjelang akhir tahun kalendar 2027.[3]
Pembinaan telah disahkan; tarikh siap masih anggaran. Penanda garis masa mewakili tahun/bulan sasaran yang diterbitkan, bukan hari pembukaan yang disahkan.
Borang 10-K tahun fiskal 2025 TVA menerbitkan 1.8 bilion dolar dibelanjakan dan 1.1 bilion dolar perbelanjaan tambahan dijangka bagi loji kitar gabungan Kingston 1,500 MW, setakat 30 September 2025. Jumlahnya kira-kira 2.9 bilion dolar. Jumlah ini ialah aritmetik ke atas jumlah projek yang didedahkan, bukan anggaran penanda aras. RFP bateri, pengembangan yang dicadangkan dan kadaran kampus yang lebih luas tidak termasuk.[3]
Borang 10-K tahun fiskal 2025 TVA menerbitkan 1.8 bilion dolar dibelanjakan dan 1.1 bilion dolar perbelanjaan tambahan dijangka bagi loji kitar gabungan Kingston 1,500 MW, setakat 30 September 2025. Jumlahnya kira-kira 2.9 bilion dolar. Jumlah ini ialah aritmetik ke atas jumlah projek yang didedahkan, bukan anggaran penanda aras. RFP bateri, pengembangan yang dicadangkan dan kadaran kampus yang lebih luas tidak termasuk. Kapasiti penjanaan diterbitkan bagi loji ganti kitar gabungan Kingston: 1500 MW. Kapasiti penjanaan elektrik yang dilaporkan pengendali; bukan pengeluaran tenaga tahunan. TVA menyatakan secara jelas bahawa ia sedang membina loji kitar gabungan 1,500 MW, dengan sasaran akhir 2027. Kapasiti itu untuk loji kitar gabungan, bukan semua unit di tapak Kingston.[3]
Hanya projek dengan pembinaan fizikal, pentauliahan atau pembukaan 2025–2026 yang didokumenkan serta kos dan keluaran elektrik khusus projek yang diterbitkan dikekalkan. Kos menggunakan skop dan mata wang yang diterbitkan; tiada anggaran penanda aras atau penukaran mata wang. MW ialah kapasiti kuasa, bukan pengeluaran elektrik tahunan. Tenaga tahunan yang dijangka, jika diberikan, ialah ramalan. Titik peta ialah lokasi loji/projek yang dilaporkan dan mungkin anggaran. Paparan inventori yang sepadan dan cadangan pengembangan yang dikecualikan bukan kapasiti tambahan.
Pembinaan tapak Kingston Energy Complex, diterbitkan pada 6 Mac 2025 bersama pengumuman pembinaan TVA. Imej itu merangkumi kompleks tenaga yang lebih luas, termasuk kerja kitar gabungan dan aeroderivatif; ia bukan gambar loji ganti yang telah siap. Kredit: pengumuman Tennessee Valley Authority melalui 3B Media News; jurugambar tidak dikenal pasti. Sumber dan galeri; media asal.