Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Start: Epoch[2] AI satellite observation dates land clearing to 1 October 2023. Completion (estimated): Epoch AI satellite observation records strong evidence Buildings 1 and 2 operational as of 2 May 2026.
Construction research 2026-10-24: Epoch’s[1] 2026-05-02 observation documents the identified building scope complete or operating, using physical observations or explicit delivery rather than an elapsed target date. Completed is limited to that scope. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “colored motion artifacts on many cooling fans” Dated observation 2026-05-02; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
Nota imej satelit Epoch AI, mengikut urutan tarikh. · sumber
Physical-stage observation dated 2026-05-02. Named completed buildings only; later expansion is not marked completed. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“colored motion artifacts on many cooling fans”
Epoch’s dated 2026-05-02 assessment: colored motion artifacts on many cooling fans Named completed buildings only; later expansion is not marked completed.
“colored motion artifacts on many cooling fans”
Epoch estimates AI hardware: Nvidia B300 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B300 chips.”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch dated observation: Satellite image shows strong evidence that Buildings 1 and 2 are…
“Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances.”
Meta Eagle Mountain in Eagle Mountain, Utah, United States is a frontier AI data center campus operated by Meta reaching 133 MW of power capacity and 151,354 H100-equivalent AI accelerators. 0
Epoch’s 2026-05-02 observation documents the identified building scope complete or operating, using physical observations or explicit delivery rather than an elapsed target date. Completed is limited to that scope. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.