Entri pertama sentiasa sumber pin. Keyakinan keseluruhan ialah purata berpemberat bagi sejauh mana setiap rujukan menyokong masa mula dan tamat yang digunakan di atas; sesebuah rujukan diambil kira separuh kurang bagi setiap 180 hari lebih lama daripada yang terbaharu.
Tarikh yang disimpan ialah anggaran penjejakan atau penanda trajektori kapasiti, bukan hari pembukaan tepat yang disahkan. Status pembinaan mengikut skop fizikal bertarikh yang dinyatakan; tiada penyempurnaan disimpulkan daripada sasaran yang telah berlalu.
Construction research 2026-10-24: Epoch’s[1] 2026-07-05 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Construction equipment present all around site.” Dated observation 2026-07-05; future trajectory rows and modeled costs are distinguished from this physical milestone.
Ada yang tertinggal atau salah? Nyatakan dengan kata-kata anda sendiri: pautan yang menyokong pin ini, tarikh mula atau tamat yang berbeza beserta sebabnya, atau fakta yang tiada atau tersilap. AI menyemaknya berbanding sumber pin ini, mencari yang lebih baik, dan menambah mana-mana halaman yang menyokong anda. Sumber pin itu sendiri tetap paling diambil kira. Gambar yang menunjukkan sesuatu yang lain, atau menunjukkannya dengan buruk, turut dilihat, dan dialihkan ke bawah atau diganti.
| 2026-07-05 |
|---|
| Penyejukan bangunan 1 kelihatan lengkap. Pemasangan penjana sandaran diteruskan bersebelahan dengan B1. Pemasangan penyejukan Bangunan 2 diteruskan. Pad konkrit penjana sandaran ada, tetapi tiada pem… |
| 2026-12-31 | Kami percaya Bangunan 1 dan 2 akan beroperasi sepenuhnya pada penghujung H2 2026 |
|---|
Nota imej satelit Epoch AI, mengikut urutan tarikh. · sumber
Physical-stage observation dated 2026-07-05. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Construction equipment present all around site.”
Epoch’s dated 2026-07-05 assessment: Construction equipment present all around site. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Construction equipment present all around site.”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing and site prep begins at least as early as July 2023.
“Land clearing and site prep begins at least as early as July 2023.”
Epoch assessment: Building 1 cooling looks complete.
“Building 1 cooling looks complete.”
Tajuk asal: Microsoft Narvik Norway AI Data Center Buildout
Microsoft Narvik Norway di Bjerkvik, Narvik, Norway ialah kampus pusat data AI sempadan yang dikendalikan oleh Nscale / Microsoft yang mencapai 92 MW kapasiti kuasa dan 265,285 pemecut AI setara H100. Kampus pusat data akan menggunakan kuasa hidro tempatan dengan kos elektrik 4 hingga 5 sen seunit berbanding sehingga 10 sen di bahagian lain di Eropah.
Dokumen pemerhatian 2026-07-05 Epoch baki pembinaan/pemasangan fizikal untuk binaan dinamakan ini. Dalam Proses tidak menyiapkan bangunan operasi lebih awal atau kapasiti masa hadapan. Kiraan kuasa dan pemecut kekal sebagai anggaran Epoch, bukan penilaian yang diperakui oleh pengendali. Kos modal 2025 dolar yang dimodelkan termasuk perkakasan pengiraan dan bukan belanjawan pembinaan asli sumber.