Northwest corner of W. Althea Ave. and N. Russell Ave., Firebaugh, Fresno County, California 93622Renewable Properties
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins12 months late55% CONFIDENCEOverall confidence: 55%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidencein 33 days
EIA 860M (interconnection.fyi[2]): unit ALP2 3.9 MW "proposed completion 1 December 2026"; the developer's May 2025 release targeted Q4 2025 for both phases.Renewable Properties is building Althea Avenue Solar Phase 2, a 5.02 MWdc (3.9 MWac) array in Fresno County for PG&E's Solar Choice program; phase 1 (6.42 MWdc) is already online and cost is not published.