ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins69% CONFIDENCEOverall confidence: 69%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidencein 44 days
Longroad's 15 September 2025 release says "commercial operations expected in 2026"; Cleanview's[4] EIA-860M row says 1 August 2026, which has passed with no energization notice found, so the last month of the stated year is used.Longroad Energy is building the 300 MWac (400 MWdc) 1000 Mile solar farm in Yoakum County, Texas, with all output contracted to Meta; construction began at financial close on 15 September 2025 and no total project cost has been published.