Intel CEO Pat Gelsinger announced the IDM 2.0 strategy and Intel Foundry Services on 23 Mar 2021, with two new Arizona fabs at about $20 billion [1].
At Intel Foundry Direct Connect on 29 April 2025 Intel said it had engaged lead customers on Intel 14A, the successor to 18A, with an early PDK [2]. On 24 July 2025 CEO Lip-Bu Tan wrote that 'there are no more blank checks' and that 14A would be built out only on confirmed customer commitments [3]. On the Q2 2026 call Tan said 14A risk production for internal products was pulled forward to the second half of 2027, with volume in 2028 [4]; CFO Dave Zinsner said customer talks had moved from evaluation to capacity [5]. Intel released the 14A 0.9 PDK in October 2026, with 1.0 targeted for Q1 2027 and customers still unnamed [6]. AEP Ohio sized its Green Chapel station for 440 MW initial and 1,560 MW peak load, but the Ohio One fab has slipped to 2031 [7].