Energy: battery storage · تم التحقق 2026-10-30
تُبرز المرحلة المعلنة فقط. تميز الأرقام والتواريخ بين المخطط والمثبت.
500 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Stein - Rapson 345 kV line","summerNetMW":500.0”
2025-04-01; requested date only, not an achieved opening.
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Stein - Rapson 345 kV line.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
يتابع هذا الدبوس الأخبار: فهو يعرض ما هو معروف الآن، وهنا ما تغيّر وما الذي أدى إليه.
تم التعديلبواسطة @ThePinGang
ITC Michigan and MISO have advanced system stability and generator interconnection engineering for the 500M USD, 500 MW / 2,000 MWh Stein-Rapson Clean Energy Storage Center in Huron County, Michigan.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date.
ITC Michigan progressed MISO DPP Definitive Planning Study Queue J2140 engineering for the facility. Features 500 MW / 2,000 MWh of utility-grade containerized lithium iron phosphate battery storage. Represents an estimated 500 million USD private clean energy development in Michigan's Thumb region. Interconnects to ITC Michigan's 345 kV Stein to Rapson transmission line. Captures high-volume Thumb wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date. The point of interconnection is Stein - Rapson 345 kV line. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
تم التعديلبواسطة @ThePinGang
… wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.
صور من القرّاء، منفصلة عن وسائط الدبوس الموثّقة بمصادر. قيّم ما أكلته أو رأيته، وفي دبوس المطعم وسّم الأطباق مباشرة على صورتك.
المدخل الأول هو دائمًا مصدر الدبوس. الثقة الإجمالية متوسط مرجّح لمدى قوة دعم كل مرجع لوقتَي البدء والانتهاء المستخدمين أعلاه؛ ويقل وزن المرجع إلى النصف عن كل 180 يومًا يسبق بها أحدث مرجع.
01-04-2025 هو تاريخ الخدمة المطلوب لسجل ربط الاتصال البيني، وليس يوم افتتاح أو تشغيل تجاري تم التحقق منه.
هل ينقص شيء أو يوجد خطأ؟ قله بكلماتك: رابط يدعم هذا الدبوس، أو تاريخ بدء أو انتهاء مختلف مع السبب، أو معلومة ينقصها أو يخطئ فيها. يفحص الذكاء الاصطناعي ذلك بمقارنته بمصادر هذا الدبوس، ويبحث عن مصادر أفضل، ويضيف أي صفحة تدعم كلامك. وتبقى مصادر الدبوس نفسه الأثقل وزنًا. كما تُفحص الصورة التي تُظهر شيئًا آخر أو تُظهره بشكل سيئ، فتُنزَّل أو تُستبدل.
العنوان الأصلي: Stein-Rapson: 500 MW Battery Interconnection Request J2590
Power storage500 MW · J2590: 500 MW requested battery storage. Queue status: Active. Requested date: 2025-04-01. Not current measured generation; No annual energy or battery MWh inferred. · source