Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
| Date | Observed status |
|---|---|
| 2024-04-20 | Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete. |
| 2024-09-13 | Building 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Buildi |
| 2025-06-01 | Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on |
| 2025-10-14 | Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in p |
| 2026-01-18 | Water vapor from cooling towers is present across Building 1-4, confirming their operation. Building 5 roof is still incomplete, but most backup generators and 5 cooling towers have been installed. |
| 2026-03-12 | Building 5 has more cooling towers installed but not complete, and the roof is almost complete. |
| 2026-05-18 | Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational. |
Epoch AI satellite-imagery notes, in date order. · المصدر
قيد الإنشاء
Digital infrastructure: AI data-center campus buildout · تم التحقق 2026-10-30
تُبرز المرحلة المعلنة فقط. تميز الأرقام والتواريخ بين المخطط والمثبت.
Epoch’s current campus estimate: 333 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 333 MW”
Physical-stage observation dated 2026-05-18. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“there is still light work around the building”
Epoch’s dated 2026-05-18 assessment: there is still light work around the building Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“there is still light work around the building”
Epoch estimates AI hardware: Google TPU v5e, Google TPU v5p, and Google TPU v6e chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v5e, Google TPU v5p, and Google TPU v6e chips.”
Epoch dated observation: Building 1 is operational.
“Building 1 is operational.”
Epoch dated observation: Building 5 has all cooling towers installed, and all other components…
“Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building.”
صور من القرّاء، منفصلة عن وسائط الدبوس الموثّقة بمصادر. قيّم ما أكلته أو رأيته، وفي دبوس المطعم وسّم الأطباق مباشرة على صورتك.
المدخل الأول هو دائمًا مصدر الدبوس. الثقة الإجمالية متوسط مرجّح لمدى قوة دعم كل مرجع لوقتَي البدء والانتهاء المستخدمين أعلاه؛ ويقل وزن المرجع إلى النصف عن كل 180 يومًا يسبق بها أحدث مرجع.
التاريخ المحفوظ عبارة عن تتبع تقديري أو علامة مسار السعة، وليس يوم افتتاح محددًا تم التحقق منه. تتبع حالة البناء النطاق المادي المؤرخ المذكور؛ لا يتم استنتاج أي اكتمال من الأهداف المنقضية.
Construction research 2026-10-24: Epoch’s[1] 2026-05-18 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “there is still light work around the building” Dated observation 2026-05-18; future trajectory rows and modeled costs are distinguished from this physical milestone.
هل ينقص شيء أو يوجد خطأ؟ قله بكلماتك: رابط يدعم هذا الدبوس، أو تاريخ بدء أو انتهاء مختلف مع السبب، أو معلومة ينقصها أو يخطئ فيها. يفحص الذكاء الاصطناعي ذلك بمقارنته بمصادر هذا الدبوس، ويبحث عن مصادر أفضل، ويضيف أي صفحة تدعم كلامك. وتبقى مصادر الدبوس نفسه الأثقل وزنًا. كما تُفحص الصورة التي تُظهر شيئًا آخر أو تُظهره بشكل سيئ، فتُنزَّل أو تُستبدل.
العنوان الأصلي: Google New Albany AI Data Center Buildout
Google New Albany في نيو ألباني، أوهايو، الولايات المتحدة هو حرم جامعي لمركز بيانات الذكاء الاصطناعي الحدودي تديره Google / Google DeepMind ويصل إلى 333 MW من سعة الطاقة و323,901 مسرع ذكاء اصطناعي مكافئ H100. 0
توثق ملاحظة Epoch's 2026-05-18 البناء/التثبيت المادي المتبقي لهذا البناء المسمى. قيد التقدم لا يكمل المباني التشغيلية السابقة أو القدرة المستقبلية. تظل أعداد القوة والمسرع تقديرات زمنية، وليست تصنيفًا معتمدًا من قبل المشغل. تتضمن التكاليف الرأسمالية النموذجية البالغة 2025 دولارًا أجهزة حسابية وليست ميزانية إنشاءات محلية المصدر.