Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
| Date | Observed status |
|---|---|
| 2023-01-01 | Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after. |
| 2025-01-01 | The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. |
| 2025-03-01 | Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but |
| 2025-11-01 | Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. |
| 2026-01-24 | Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have s |
| 2026-06-01 | Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining. |
| 2026-08-06 | On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in |
| 2026-11-01 | Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. |
| 2026-12-31 | Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is abou |
| 2027-12-01 | All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is exclu |
Epoch AI satellite-imagery notes, in date order. · المصدر
قيد الإنشاء
Digital infrastructure: AI data-center campus buildout · تم التحقق 2026-10-30
تُبرز المرحلة المعلنة فقط. تميز الأرقام والتواريخ بين المخطط والمثبت.
Epoch’s current campus estimate: 157 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 157 MW”
Physical-stage observation dated 2026-08-06. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“building 9 is under construction”
Epoch’s dated 2026-08-06 assessment: building 9 is under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“building 9 is under construction”
Epoch estimates AI hardware: Huawei Ascend 910C chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Huawei Ascend 910C chips.”
Epoch dated observation: Land clearing begins, with the east campus being the first of the three.
“Land clearing begins, with the east campus being the first of the three.”
Epoch dated observation: On the north campus, building 5 is structurally complete but not…
“On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars.”
صور من القرّاء، منفصلة عن وسائط الدبوس الموثّقة بمصادر. قيّم ما أكلته أو رأيته، وفي دبوس المطعم وسّم الأطباق مباشرة على صورتك.
المدخل الأول هو دائمًا مصدر الدبوس. الثقة الإجمالية متوسط مرجّح لمدى قوة دعم كل مرجع لوقتَي البدء والانتهاء المستخدمين أعلاه؛ ويقل وزن المرجع إلى النصف عن كل 180 يومًا يسبق بها أحدث مرجع.
التاريخ المحفوظ عبارة عن تتبع تقديري أو علامة مسار السعة، وليس يوم افتتاح محددًا تم التحقق منه. تتبع حالة البناء النطاق المادي المؤرخ المذكور؛ لا يتم استنتاج أي اكتمال من الأهداف المنقضية.
Construction research 2026-10-24: Epoch’s[1] 2026-08-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “building 9 is under construction” Dated observation 2026-08-06; future trajectory rows and modeled costs are distinguished from this physical milestone.
هل ينقص شيء أو يوجد خطأ؟ قله بكلماتك: رابط يدعم هذا الدبوس، أو تاريخ بدء أو انتهاء مختلف مع السبب، أو معلومة ينقصها أو يخطئ فيها. يفحص الذكاء الاصطناعي ذلك بمقارنته بمصادر هذا الدبوس، ويبحث عن مصادر أفضل، ويضيف أي صفحة تدعم كلامك. وتبقى مصادر الدبوس نفسه الأثقل وزنًا. كما تُفحص الصورة التي تُظهر شيئًا آخر أو تُظهره بشكل سيئ، فتُنزَّل أو تُستبدل.
العنوان الأصلي: Huawei Wuhu AI Data Center Buildout
Huawei Wuhu في Wuhu، Anhui، الصين، هو حرم جامعي لمركز بيانات الذكاء الاصطناعي الحدودي تديره Huawei ويصل إلى 457 MW من سعة الطاقة و221,924 مسرع الذكاء الاصطناعي المكافئ H100. 0
توثق ملاحظة Epoch's 2026-08-06 البناء/التثبيت المادي المتبقي لهذا البناء المسمى. قيد التقدم لا يكمل المباني التشغيلية السابقة أو القدرة المستقبلية. تظل أعداد القوة والمسرع تقديرات زمنية، وليست تصنيفًا معتمدًا من قبل المشغل. تتضمن التكاليف الرأسمالية النموذجية البالغة 2025 دولارًا أجهزة حسابية وليست ميزانية إنشاءات محلية المصدر.