Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · المصدر
| Date | Observed status |
|---|---|
| 2023-10-31 | Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave |
| 2025-05-28 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) f |
| 2025-08-29 | [A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project |
| 2025-10-27 | The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-f |
| 2025-11-24 | [This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready |
| 2026-03-27 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, t |
| 2026-06-30 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and |
| 2026-12-31 | According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the seco |
| 2027-06-01 | According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2 |
Epoch AI satellite-imagery notes, in date order. · المصدر
قيد الإنشاء
Digital infrastructure: AI data-center campus buildout · تم التحقق 2026-10-30
تُبرز المرحلة المعلنة فقط. تميز الأرقام والتواريخ بين المخطط والمثبت.
Epoch’s current campus estimate: 68 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 68 MW”
Physical-stage observation dated 2026-06-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 construction is well underway”
Epoch’s dated 2026-06-30 assessment: Building 3 construction is well underway Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 construction is well underway”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: CoreWeave was not leased yet at this site, but this is the…
“CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.”
Epoch dated observation: According to satellite imagery, Building 2 is fully roofed and shell…
“According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.”
صور من القرّاء، منفصلة عن وسائط الدبوس الموثّقة بمصادر. قيّم ما أكلته أو رأيته، وفي دبوس المطعم وسّم الأطباق مباشرة على صورتك.
المدخل الأول هو دائمًا مصدر الدبوس. الثقة الإجمالية متوسط مرجّح لمدى قوة دعم كل مرجع لوقتَي البدء والانتهاء المستخدمين أعلاه؛ ويقل وزن المرجع إلى النصف عن كل 180 يومًا يسبق بها أحدث مرجع.
التاريخ المحفوظ عبارة عن تتبع تقديري أو علامة مسار السعة، وليس يوم افتتاح محددًا تم التحقق منه. تتبع حالة البناء النطاق المادي المؤرخ المذكور؛ لا يتم استنتاج أي اكتمال من الأهداف المنقضية.
Construction research 2026-10-24: Epoch’s[1] 2026-06-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 construction is well underway” Dated observation 2026-06-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
هل ينقص شيء أو يوجد خطأ؟ قله بكلماتك: رابط يدعم هذا الدبوس، أو تاريخ بدء أو انتهاء مختلف مع السبب، أو معلومة ينقصها أو يخطئ فيها. يفحص الذكاء الاصطناعي ذلك بمقارنته بمصادر هذا الدبوس، ويبحث عن مصادر أفضل، ويضيف أي صفحة تدعم كلامك. وتبقى مصادر الدبوس نفسه الأثقل وزنًا. كما تُفحص الصورة التي تُظهر شيئًا آخر أو تُظهره بشكل سيئ، فتُنزَّل أو تُستبدل.
العنوان الأصلي: CoreWeave Ellendale ND AI Data Center Buildout
توثق ملاحظة Epoch's 2026-06-30 البناء/التثبيت المادي المتبقي لهذا البناء المسمى. قيد التقدم لا يكمل المباني التشغيلية السابقة أو القدرة المستقبلية. تظل أعداد القوة والمسرع تقديرات زمنية، وليست تصنيفًا معتمدًا من قبل المشغل. تتضمن التكاليف الرأسمالية النموذجية البالغة 2025 دولارًا أجهزة حسابية وليست ميزانية إنشاءات محلية المصدر.
الحرم الجامعي للتدريب والاستدلال على الذكاء الاصطناعي الحدودي الفائق النطاق الذي تم تتبعه بواسطة Epoch AI مع آثار أقدام الأقمار الصناعية المشروحة (8 أجزاء مادية).