يتابع هذا الدبوس الأخبار: فهو يعرض ما هو معروف الآن، وهنا ما تغيّر وما الذي أدى إليه.
تم التعديلبواسطة @ThePinGang
قبل
2027. Equinor identifies an expected commercial-operation date in 2027 for Empire Wind 1.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
تم التعديلبواسطة @ThePinGang
تم التعديلبواسطة @ThePinGang
قبل
قبل
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
تم التعديلبواسطة @ThePinGang
قبل
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
تم التعديلبواسطة @ThePinGang
قبل
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
تم التعديلبواسطة @ThePinGang
قبل
قبل
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Operator project overview confirms permitting and development context.
EIA August 2026 generator inventory, plant ID 68443: Empire Wind 1, Kings County, NY. Included 1 new/recent generating units with a summed nameplate rating of 810 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
GEM August 2026 snapshot: under construction. 816 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Wind.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Additional source view; compare phase coverage and rating conventions before combining figures.
تم التعديلبواسطة @ThePinGang
قبل
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Operator project overview confirms permitting and development context.
EIA August 2026 generator inventory, plant ID 68443: Empire Wind 1, Kings County, NY. Included 1 new/recent generating units with a summed nameplate rating of 810 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
GEM August 2026 snapshot: under construction. 816 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Wind.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
هذه صور القرّاء، منفصلة عن وسائط الدبوس الموثّقة بمصادر.
المدخل الأول هو دائمًا مصدر الدبوس. الثقة الإجمالية متوسط مرجّح لمدى قوة دعم كل مرجع لوقتَي البدء والانتهاء المستخدمين أعلاه؛ ويقل وزن المرجع إلى النصف عن كل 180 يومًا يسبق بها أحدث مرجع.
الموعد المستهدف المنشور: 2027. الإنشاء موثّق، لكن هذه المحطة المستقبلية للإنجاز/التشغيل تقديرية. والتاريخ علامة زمنية لنهاية السنة/الشهر وليس يوم افتتاح مؤكدًا. المصدر: https://www.equinor[2].com/news/20250102-securing-financial-close-empire-wind[3]-1
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind[3] 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
هل ينقص شيء أو يوجد خطأ؟ قله بكلماتك: رابط يدعم هذا الدبوس، أو تاريخ بدء أو انتهاء مختلف مع السبب، أو معلومة ينقصها أو يخطئ فيها. يفحص الذكاء الاصطناعي ذلك بمقارنته بمصادر هذا الدبوس، ويبحث عن مصادر أفضل، ويضيف أي صفحة تدعم كلامك. وتبقى مصادر الدبوس نفسه الأثقل وزنًا. كما تُفحص الصورة التي تُظهر شيئًا آخر أو تُظهره بشكل سيئ، فتُنزَّل أو تُستبدل.
العنوان الأصلي: Empire Wind 1 — estimated target 2027
2027. تحدد Equinor تاريخًا متوقعًا للتشغيل التجاري في 2027 لمشروع Empire Wind 1.[2]
الإنشاء مؤكَّد؛ أما موعد الاكتمال فلا يزال تقديريًا. تمثّل العلامة الزمنية السنة/الشهر المستهدف المنشور، وليس يوم افتتاح مؤكدًا.
تصف Equinor إجمالي الإنفاق الرأسمالي لمشروع Empire Wind بأنه يُقدَّر بـ 5 مليار دولار بعد الإعفاءات الضريبية، ويشمل 54 توربينًا بأساسات ثابتة ونقطة وصول الكابل في بروكلين. وهذا تقدير مُعدَّل بعد الإعفاءات الضريبية، وليس التكلفة الإجمالية قبل الإعفاءات ولا حزمة التمويل التي تتجاوز 3 مليار دولار. تبلغ قدرة التوليد لمشروع Empire Wind 1 ما قدره 810 ميغاواط، والإنشاء البحري موثّق؛ ويُستهدف التشغيل الكامل في 2027.[2][3]
تنشر Equinor في 2 يناير 2025 إجمالي استثمار رأسمالي متوقعًا يبلغ نحو 5 مليار دولار أمريكي، يشمل رسوم استخدام South Brooklyn Marine Terminal وأثر الإعفاءات الضريبية المتوقعة للاستثمار مستقبلًا. أما حزمة التمويل التي تتجاوز 3 مليار دولار أمريكي فهي منفصلة. القدرة المنشورة لمشروع توليد الكهرباء Empire Wind 1: 810 ميغاواط. الأساس: قدرة توليد الكهرباء التي أعلنتها الجهة المشغّلة؛ وليست الإنتاج السنوي للطاقة. ويحدد الإعلان الرسمي للمشروع 810 ميغاواط ويفصل بين التمويل والإنفاق الرأسمالي للمشروع.[2]
تعرض صفحة الإنشاء لدى الجهة المشغّلة لمشروع Empire Wind أعمال التركيب البحرية وتحدد أن محطة التحويل رُكّبت في يناير 2026. ومن المتوقع أن يعمل Empire Wind 1 بالكامل في 2027. وللموقع البحري ولـ South Brooklyn Marine Terminal وظيفتان مختلفتان؛ فالمحطة ليست موقع التوليد.[3]
لا يُحتفظ إلا بالمشاريع الموثَّق فيها إنشاء مادي أو تشغيل تجريبي أو افتتاح في 2025–2026 والتي نُشرت لها تكاليف وقدرة كهربائية خاصة بالمشروع. تستخدم التكاليف النطاق والعملة المنشورين؛ ولا توجد تقديرات مرجعية ولا تحويلات عملة. الميغاواط قدرة طاقة وليس إنتاج الكهرباء السنوي. والطاقة السنوية المتوقعة، حيثما ذُكرت، توقّع. نقطة الخريطة موقع مُبلَّغ عنه للمحطة/المشروع وقد تكون تقريبية. وعروض الجرد المطابقة ومقترحات التوسعة المستبعدة ليست قدرة قابلة للجمع.
صورة لأعمال التركيب البحرية من صفحة مشروع Empire Wind لدى الجهة المشغّلة. المصدر/الحقوق: Empire Wind / Equinor; لم يُذكر اسم المصوّر في صفحة المصدر. صفحة المصدر; الصورة الأصلية من الجهة المشغّلة.
صورة لتركيب محطة التحويل البحرية لمشروع Empire Wind نُشرت في معرض الإنشاء لدى الجهة المشغّلة؛ وتذكر الصفحة أن التركيب تم في يناير 2026. المصدر/الحقوق: Empire Wind / Equinor; لم يُذكر اسم المصوّر في صفحة المصدر. صفحة المصدر; الصورة الأصلية من الجهة المشغّلة.
صورة لأعمال التركيب البحرية من صفحة مشروع Empire Wind لدى الجهة المشغّلة. المصدر/الحقوق: Empire Wind / Equinor; لم يُذكر اسم المصوّر في صفحة المصدر. صفحة المصدر لدى الجهة المشغّلة; الصورة الأصلية.
صورة لتركيب محطة التحويل البحرية لمشروع Empire Wind نُشرت في معرض الإنشاء لدى الجهة المشغّلة؛ وتذكر الصفحة أن التركيب تم في يناير 2026. المصدر/الحقوق: Empire Wind / Equinor; لم يُذكر اسم المصوّر في صفحة المصدر. صفحة المصدر لدى الجهة المشغّلة; الصورة الأصلية.
طبقة صخرية تحت الماء حول أساس في مشروع Empire Wind. لم يُذكر تاريخ الالتقاط بشكل منفصل. المصدر/الحقوق: Empire Wind / Equinor; لم يُذكر اسم المصوّر. المصدر والمعرض; الوسائط الأصلية.
أعمال الكابلات البينية في مشروع Empire Wind، من معرض التركيب البحري الرسمي. لم يُذكر تاريخ الالتقاط بشكل منفصل. المصدر/الحقوق: Empire Wind / Equinor; لم يُذكر اسم المصوّر. المصدر والمعرض; الوسائط الأصلية.