DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins4 months late63% CONFIDENCEOverall confidence: 63%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidencein 1 day
Cleanview's EIA-based listing gives November 2026; the earlier ERCOT date (20 Jul 2026, Infrasure[2]) and the TDLR completion date (1 Aug 2026) have passed without any announcement of commercial operation.Jupiter Power's Callisto II battery in Houston, Harris County is filed with Texas regulators as a 300 MW two-hour system and sits in ERCOT's queue at about 406 MW; a 258 million USD construction facility closed in April 2026 jointly with Pamela Heights I, and no project-only cost is published.