Documented physical milestone or dated progress/reporting marker. Period-end dates represent only the reported month/quarter; they do not invent an exact operation date. Source estimates are labelled and not treated as confirmed future opening dates.
TVA June 30, 2026 Form 10-Q discloses $276 million spent and up to $155 million additional spending on its 200 MW Allen aeroderivative addition. Sum: up to $431 million, explicitly calculated from published project figures. This is an upper forecast spending envelope, not a quoted fixed-price contract. Allen aeroderivative addition: published generating capacity 200 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly reports constructing this 200 MW project after a December 2025 air permit. The planning-only Lagoon Creek project is separate and excluded.[1]
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
TVA June 30, 2026 Form 10-Q discloses $276 million spent and up to $155 million additional spending on its 200 MW Allen aeroderivative addition. Sum: up to $431 million, explicitly calculated from published project figures. This is an upper forecast spending envelope, not a quoted fixed-price contract.[2]
TVA June 30, 2026 Form 10-Q discloses $276 million spent and up to $155 million additional spending on its 200 MW Allen aeroderivative addition. Sum: up to $431 million, explicitly calculated from published project figures. This is an upper forecast spending envelope, not a quoted fixed-price contract. Allen aeroderivative addition: published generating capacity 200 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly reports constructing this 200 MW project after a December 2025 air permit. The planning-only Lagoon Creek project is separate and excluded.[2]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.