Aligned Data Centers operates the 1.36B USD, 50.4Aligned’s October 2024 ORD-01 specification lists 36 MW (36 MW IT capacity) Phase 1 hyperscale facility in Northlake, Cook County, Illinois, providing high-efficiency Delta Cube liquid-cooling infrastructure for enterprise AI workloads.and 220,000 gross sqft at 505 Northwest Avenue, Northlake. The 18.5 acres and approximately 72 MW at full build are campus scope, separate from ORD-02.
Aligned Data Centers commissioned The April 19, 2022 launch release described 48 MW, expandable to about 60 MW; the ORD-01 later sheet instead lists 36 MW. The discrepancy is explicit. The old 50.4 MW hyperscale facility on its 18-acre campus in Northlake, Illinois. Features 36 MW demand and $1.36B were scaled estimates. No measured daily water or energy is published. Timeline: Confirmed April 19, 2022 first-phase launch announcement, not the later specification date. Current rating follows the opened October 2024 operator sheet. Operator gallery image of critical ORD-01 lobby. Publication does not establish current IT load across 131,500 square feet utilizing proprietary Delta Cube waterless cooling technology. Represents an estimated 1.368 billion USD capital investment supporting mission-critical enterprise cloud MW, exact commissioning day or measured water/energy consumption. Credit: Aligned Data Centers. Operator gallery image of ORD-01 building exterior and rooftop equipment. Publication does not establish current IT MW, exact commissioning day or measured water/energy consumption. Credit: Aligned Data Centers. Operator gallery image of ORD-01 building entrance/exterior. Publication does not establish current IT MW, exact commissioning day or measured water/energy consumption. Credit: Aligned Data Centers. Operator gallery image of ORD-01 interior reception area. Publication does not establish current IT MW, exact commissioning day or measured water/energy consumption. Credit: Aligned Data Centers. Operator gallery image of ORD-01 meeting room and high-density compute. Interconnects to ComEd's high-voltage electrical grid via dedicated on-site substations in suburban Cook County. Expands Chicago's position as a premier Tier 1 data center hub with ultra-low latency fiber connectivity. Timeline: operating facility energized in April 2022 (confirmed) following grid interconnection commissioning.lobby. Publication does not establish current IT MW, exact commissioning day or measured water/energy consumption. Credit: Aligned Data Centers. Operator gallery image of ORD-01 exterior aerial view. Publication does not establish current IT MW, exact commissioning day or measured water/energy consumption. Credit: Aligned Data Centers.
Bearbeitetvon @ThePinGang
… data center hub with ultra-low latency fiber connectivity. Timeline: operating facility energized in April 2022 (confirmed) following grid interconnection commissioning.
Fotos von Lesern, getrennt von den belegten Medien des Pins. Bewerte, was du gegessen oder gesehen hast, und markiere bei einem Restaurant-Pin die Gerichte direkt auf deinem Foto.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Bestätigte Ankündigung der ersten Phase am 19. April 2022, nicht das spätere Spezifikationsdatum. Die aktuelle Bewertung folgt dem im Oktober 2024 geöffneten Betreiberblatt.
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: Aligned ORD-01: 36 MW Operator Specification, 220,000 Sqft