Angekündigt
Energy: battery storage · Geprüft am 2026-10-30
Nur die gemeldete Phase ist hervorgehoben. Angaben und Termine unterscheiden geplante und nachgewiesene Zustände.
500 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Stein - Rapson 345 kV line","summerNetMW":500.0”
2025-04-01; requested date only, not an achieved opening.
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Stein - Rapson 345 kV line.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
Dieser Pin folgt den Nachrichten: Er zeigt den aktuellen Stand, und hier steht, was sich geändert hat und wodurch.
Bearbeitetvon @ThePinGang
ITC Michigan and MISO have advanced system stability and generator interconnection engineering for the 500M USD, 500 MW / 2,000 MWh Stein-Rapson Clean Energy Storage Center in Huron County, Michigan.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date.
ITC Michigan progressed MISO DPP Definitive Planning Study Queue J2140 engineering for the facility. Features 500 MW / 2,000 MWh of utility-grade containerized lithium iron phosphate battery storage. Represents an estimated 500 million USD private clean energy development in Michigan's Thumb region. Interconnects to ITC Michigan's 345 kV Stein to Rapson transmission line. Captures high-volume Thumb wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date. The point of interconnection is Stein - Rapson 345 kV line. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Bearbeitetvon @ThePinGang
… wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.
Fotos von Lesern, getrennt von den belegten Medien des Pins. Bewerte, was du gegessen oder gesehen hast, und markiere bei einem Restaurant-Pin die Gerichte direkt auf deinem Foto.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Der 01.04.2025 ist das gewünschte Inbetriebnahmedatum des Verbindungsdatensatzes und kein verifizierter Eröffnungs- oder kommerzieller Betriebstag.
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: Stein-Rapson: 500 MW Battery Interconnection Request J2590
Power storage500 MW · J2590: 500 MW requested battery storage. Queue status: Active. Requested date: 2025-04-01. Not current measured generation; No annual energy or battery MWh inferred. · source