Energy: withdrawn interconnection request · Geprüft am 2026-10-30
Nur die gemeldete Phase ist hervorgehoben. Angaben und Termine unterscheiden geplante und nachgewiesene Zustände.
600.0 MW former requested power; not current generation or battery operation.
“"summerNetMW":600.0”
2026-10-30: withdrawal recorded in the opened queue. The actual withdrawal day is not published.
“"applicationStatus":"Withdrawn"”
Withdrawn request; this does not establish site-wide project cancellation.
“"applicationStatus":"Withdrawn"”
Solar; point of interconnection Smalling.
“"fuelType":"Solar"”
Withdrawal recorded in MISO queue (date checked; withdrawal day unpublished)
“"applicationStatus":"Withdrawn"”
Dieser Pin folgt den Nachrichten: Er zeigt den aktuellen Stand, und hier steht, was sich geändert hat und wodurch.
Bearbeitetvon @ThePinGang
… no four-hour duration or battery MWh is inferred. The MISO queue was checked on October 30, 2026 and records this request as withdrawn. The actual withdrawal date is not published; the timeline milestone records the date checked.
Bearbeitetvon @ThePinGang
Smalling Solar Energy LLC has completed MISO Definitive Planning Studies and local zoning review for the 620M USD, 600 MWac Smalling Clean Solar Farm in Richland Parish, Louisiana.J2519 is a 600 MW photovoltaic generation interconnection request in Richland, LA. The grid operator lists its queue status as Withdrawn. The requested in-service date is 2026-10-31; this is a planning date.
Smalling Solar Energy finalized MISO DPP generatorJ2519 is a 600 MW photovoltaic generation interconnection queue studies. Supplies 600 MWac of single-axis tracking bifacial solar photovoltaic capacity across 4,200 acres. Represents an estimated 620 million USD clean energy capital development in northeastern Louisiana. Directly interconnects to Entergy Louisiana's 230/500 kV Rayville to Franklin transmission line. Generates approximately 1,180,000 MWh annually, delivering economic development and carbon-free energy torequest in Richland, LA. The grid operator lists its queue status as Withdrawn. The requested in-service date is 2026-10-31; this is a planning date. The point of interconnection is Smalling. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the Delta region. Timeline: planned project targeting commercial operation in April 2029 (estimated) under MISO interconnection queue and state regulatory schedules.cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Bearbeitetvon @ThePinGang
… development and carbon-free energy to the Delta region. Timeline: planned project targeting commercial operation in April 2029 (estimated) under MISO interconnection queue and state regulatory schedules.
Fotos von Lesern, getrennt von den belegten Medien des Pins. Bewerte, was du gegessen oder gesehen hast, und markiere bei einem Restaurant-Pin die Gerichte direkt auf deinem Foto.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: Smalling: 600 MW Solar Interconnection Request J2519 — Withdrawn
Die MISO-Warteschlange wurde am 30. Oktober 2026 überprüft und verzeichnet diese Anfrage als zurückgezogen. Das tatsächliche Austrittsdatum wird nicht veröffentlicht; Der Zeitleistenmeilenstein zeichnet das überprüfte Datum auf.[1]
Power generation600 MW · J2519: 600 MW requested photovoltaic generation. Queue status: Withdrawn. Requested date: 2026-10-31. Not current measured generation; withdrawn request. No annual energy or battery MWh inferred. · source