Angekündigt
Energy: battery storage · Geprüft am 2026-10-30
Nur die gemeldete Phase ist hervorgehoben. Angaben und Termine unterscheiden geplante und nachgewiesene Zustände.
200 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Hamilton","summerNetMW":200.0”
2027-01-31; requested date only, not an achieved opening.
“"projectNumber":"J3296","queueDate":"2024-04-17T04:00:00+00:00","inService":"2027-01-31T05:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; Hamilton.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3296","queueDate":"2024-04-17T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3296","queueDate":"2024-04-17T04:00:00+00:00","inService":"2027-01-31T05:00:00+00:00"”
Dieser Pin folgt den Nachrichten: Er zeigt den aktuellen Stand, und hier steht, was sich geändert hat und wodurch.
Bearbeitetvon @ThePinGang
Broad Reach Power development of the Hamilton Clean Energy Storage Facility in Hamilton County, Illinois. TheJ3296 is a 200 MW / 800 MWh grid-scale energy storage project provides critical capacity, frequency response, and local peak load shaving across the Ameren Illinois service territory within the MISO wholesale electricity market.battery storage interconnection request in Hamilton, IL. The grid operator lists its queue status as Active. The requested in-service date is 2027-01-31; this is a planning date.
Broad Reach Power advanced engineering and county development reviews for the Hamilton Clean Energy Storage Facility. Features a 200 MW / 800 MWh four-hour utility-scale battery energy storage system. RepresentsJ3296 is a 200 MW battery storage interconnection request in Hamilton, IL. The grid operator lists its queue status as Active. The requested in-service date is 2027-01-31; this is a 210 million USD capital project supporting grid reliability in southern Illinois. Connects to Ameren Illinois transmission lines serving the wholesale MISO electricity market. Delivers fast-ramping frequency response, voltage support, and local peak load shaving. Timeline: planned project targeting commercial operation in January 2027 (estimated) under regional grid interconnection queue and state regulatory schedules.planning date. The point of interconnection is Hamilton. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Bearbeitetvon @ThePinGang
… response, voltage support, and local peak load shaving. Timeline: planned project targeting commercial operation in January 2027 (estimated) under regional grid interconnection queue and state regulatory schedules.
Bearbeitetvon @ThePinGang
Fotos von Lesern, getrennt von den belegten Medien des Pins. Bewerte, was du gegessen oder gesehen hast, und markiere bei einem Restaurant-Pin die Gerichte direkt auf deinem Foto.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: Hamilton: 200 MW Battery Interconnection Request J3296
Power storage200 MW · J3296: 200 MW requested battery storage. Queue status: Active. Requested date: 2027-01-31. Not current measured generation; No annual energy or battery MWh inferred. · source