About 100 acres of ERCOR's land (500-acre property per Times-Tribune; 548 acres per WVIA)
“The data centers would encompass about 100 acres of ERCOR’s land, LaFratte said.”
Proposed; no data center approved, no final decision made
“No final decision has been made on the proposed data centers.”
Nine data centers (ERCOR Triboro); DeNaples seven-building plan withdrawn
“There are now nine data centers proposed in the borough after ERCOR Triboro, a limited liability company under St. Louis-based Sansone Group, applied to change its land use from four 1-million-square-foot warehouses.”
Sansone Group buys about 500 acres from DeNaples (price reported as $80 million)
“Sansone bought 500 acres from DeNaples last year for $80 million.”
Council adopts then denies data center zoning amendment (CM-2 conditional use)
“Council initially adopted but then denied the zoning amendment addressing data centers amid uproar from the crowd.”
There’s anger, there’s resentment, frustration, because we go to these meetings and it feels like we’re not being heard,
That ordinance was well thought out. It was developed over eight months.
Grossman and PPL Spokesperson Dana Burns both said there are nondisclosure agreements in place
| PPL Electric Utilities confirms data centers spurred transmission project in Lackawanna County · 22.04.2026 | -0.20 |
|---|---|
| Olyphant settles DeNaples lawsuit and confirms data center regulations · 10.06.2026 | 0.20 |
| Olyphant residents rally over proposed TriBoro data centers · 03.08.2026 | -0.70 |
Dieser Pin folgt den Nachrichten: Er zeigt den aktuellen Stand, und hier steht, was sich geändert hat und wodurch.
Bearbeitetvon @ThePinGang
Olyphant received two separate data-center proposals:A June 10, 2026 report says Triboro Commerce Park LLC sought seven buildings on over 400 acres, whilewithdrew its seven-building plan. A separate ERCOR Triboro proposed proposal sought nine buildings on roughly 500 adjacent acres.data centers on a 500-acre property.
Olyphant received two separate data-center proposals:Olyphant’s engineer confirmed withdrawal of Triboro Commerce Park LLC sought seven buildings on over 400 acres, while ERCOR TriboroPark’s seven-building plan. ERCOR Triboro, a Sansone Group company, separately proposed nine buildings on roughly 500 adjacent acres. The proposals have separate developers and applications. A combined 1,500 MW capacity, USD 14.25 billion construction budget and achieved construction milestone aredata centers, occupying about 100 acres of its 500-acre property. The zoning settlement did not established by this report.approve a campus.
Bearbeitetvon @ThePinGang
Two separate developers are separately proposing to build 16 data centers in total east of the Casey Highway. \n First, in early April,Olyphant received two separate data-center proposals: Triboro Commerce Park LLC, a company associated with DeNaples, submitted a plan to develop 7 data centersLLC sought seven buildings on just over 400 acres of the roughly 1,000-acre CM-2 zone. In late April, the company also filed a land-use appeal and a petition for an emergency injunction in Lackawanna County Court of Common Pleas asking the court to overturn Olyphant Borough Council's decision declaring its zoning ordinance invalid via a curative amendment, citing the action unlawfully excludes data centers — a further signal of its intent to build. \n Then, on May 4, Olyphant received a zoning application fromacres, while ERCOR Triboro, a limited liability company under Sansone Group, to change its land use from four warehouses toTriboro proposed nine data centers. Their campus spans aboutbuildings on roughly 500 acres and is adjacent to DeNaples land.acres.
Electrical Load: 1,500 MW planned utility capacity Olyphant received two separate data-center proposals: Triboro Commerce Park LLC sought seven buildings on the Pennsylvania / PJM grid. Site & Facility Footprint: 900 acres in Olyphant Borough, Lackawanna County, Pennsylvania. Water Demand: 1.80 MGD (estimated).over 400 acres, while ERCOR Triboro proposed nine buildings on roughly 500 adjacent acres. The proposals have separate developers and applications. A combined 1,500 MW capacity, USD 14.25 billion construction budget and achieved construction milestone are not established by this report.
Fotos von Lesern, getrennt von den belegten Medien des Pins. Bewerte, was du gegessen oder gesehen hast, und markiere bei einem Restaurant-Pin die Gerichte direkt auf deinem Foto.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Das Pin-Datum 2026-06-10 stimmt mit dem Times-Tribune-Bericht überein. ERCOR's application date is not given; no completion target published.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: Olyphant Triboro Plans: DeNaples Proposal Withdrawn, ERCOR Proposal Separate
Der Bezirk Olyphant im Lackawanna County verfügt über einen Bebauungsbezirk von etwa 1.000 Acres, in dem Rechenzentren nur unter Vorbehalt genutzt werden können. Der Plan von Triboro Commerce Park mit sieben Rechenzentren wurde im Juni 2026 zurückgezogen, während ERCOR Triboro, ein Unternehmen der Sansone-Gruppe, den Bau von neun Rechenzentren auf etwa 100 Hektar seines Grundstücks beantragte. In der Einigung des Rates vom Juni 2026 wurde kein Campus genehmigt, und die Bewohner organisieren sich gegen die Pläne.
Der Ingenieur von Olyphant bestätigte die Rücknahme des Sieben-Gebäude-Plans des Triboro Commerce Park. ERCOR Triboro, ein Unternehmen der Sansone-Gruppe, schlug separat neun Rechenzentren vor, die etwa 100 Hektar seines 500 Hektar großen Grundstücks belegen. Der Bebauungsplan genehmigte keinen Campus.[1]
Council votes 6-0 to settle Triboro Commerce Park lawsuit; amendment recognized
“Council voted 6-0 on a resolution that ended a lawsuit from Triboro Commerce Park LLC”
Triboro Commerce Park's seven-data-center plan confirmed withdrawn
“borough engineer Lou LaFratte confirmed the commerce park subsequently withdrew those plans”
Stop Olyphant Data Centers rally at Fern Hill Park
“gathered Sunday afternoon at Fern Hill Park in Olyphant to voice their opposition and share information with the community.”