Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · Quelle
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · Quelle
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · Quelle
| Date | Observed status |
|---|---|
| 2024-12-20 | Land clearing begins. |
| 2025-10-19 | Foundations are underway for the main buildings, and the overall layout aligns with the [architectural renderings](https://engineering.fb.com/2025/09/29/data-infrastructure/metas-infrastructure-evolut |
| 2026-04-19 | Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress. |
| 2026-12-01 | New [power stations](https://drive.google.com/file/d/1D4eUHwEuirNi0g3IU_xGOti3PcC8fcXi/view?usp=sharing) are in service for a 1.8 GW load at Holly Ridge. However, the data center is still not operatio |
| 2028-01-01 | First phase is operational, based on a [Meta blog post](https://drive.google.com/file/d/1PmFNgOwkPepwjpGIbNUuPJP0LNgIqe7l/view?usp=sharing). We assume that this aligns with the three natural gas turbi |
Epoch AI satellite-imagery notes, in date order. · Quelle
Im Bau
Data center · Geprüft am 2026-10-31
Nur die gemeldete Phase ist hervorgehoben. Angaben und Termine unterscheiden geplante und nachgewiesene Zustände.
$10 billion
“Meta Selects Northeast Louisiana as Site of $10 Billion Artificial Intelligence Optimized Data Center”
500 or more direct new jobs; 5,000 construction workers at peak
“Meta projects the data center will support 500 or more direct new jobs in Richland Parish.”
4 million square feet
“Expansive technology campus will occupy 4 million square feet on the 2,250-acre former Franklin Farm mega site.”
3,650 acres (from 2,250 at announcement)
“The gigantic Richland Parish site started at 2,250 acres in December 2024 and will now be expanded to 3,650 acres”
1,632 MW IT
“supported by 1,632 MW of IT power”
Under construction (Epoch status; Buildings 1-2 roofed, 3 and 6 in progress)
“Meta Hyperion is an AI data center under construction”
Meta announces Richland Parish AI data center
“Project is expected to result in 500 or more direct new jobs, more than 1,000 indirect jobs and 5,000 construction workers at peak.”
Land clearing begins (satellite)
“Land clearing begins.”
Meta's investment establishes the region as an anchor in Louisiana's rapidly expanding tech sector, revitalizes one of our state's beautiful rural areas, and creates opportunities for Louisiana workers to fill high-paying jobs of the future.
And the truth is there's just a lot of things that I cannot verify at this moment
The process is being expedited, allowing Energy to bypass the Request for Proposal competitive bidding process that is normally required for projects of this scale
We've been working closely with Entergy since early on-site planning to ensure our power needs are met and, importantly, so that Entergy's other consumers aren't paying our costs
Even the cost of building a natural gas power plant has more or less doubled over the last 10 years, and it might be more than that actually
| Meta Selects Northeast Louisiana as Site of $10 Billion AI Data Center · 04.12.2024 | 0.90 |
|---|---|
| Affordable energy advocates urge PSC to wait to vote · 15.08.2025 | -0.60 |
| La. regulators approve Entergy power plants for Meta's AI data center · 20.08.2025 | -0.40 |
| Meta triples order of gas-fired power plants · 30.03.2026 | 0.40 |
| Advocates cite lack of transparency, rising costs as regulators fast-track second Meta data center · 21.04.2026 | -0.60 |
Fotos von Lesern, getrennt von den belegten Medien des Pins. Bewerte, was du gegessen oder gesehen hast, und markiere bei einem Restaurant-Pin die Gerichte direkt auf deinem Foto.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Start ist Epochs erste per Satellit erfasste Landräumung (20. Dezember 2024); Meta sagte, dass die Arbeiten an der Website im Dezember 2024 beginnen würden. Das einzige veröffentlichte Fertigstellungsziel ist „bis 2030“ (Jahresgenauigkeit), daher wird „endDate“ auf Null gelassen.
Construction research 2026-10-24: Epoch’s[1] 2026-04-19 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 and 6 roof and cooling in progress.” Dated observation 2026-04-19; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: Meta Hyperion AI Data Center Buildout
Der Hyperion-KI-Campus von Meta auf dem ehemaligen Megastandort Franklin Farm in Richland Parish, Louisiana, befindet sich im Bau: Die Satellitenaufzeichnungen von Epoch zeigen, dass das Land im Dezember 2024 gerodet wurde, die Fundamente bis Oktober 2025 und die Dächer der Gebäude 1 und 2 bis April 2026 fertiggestellt wurden. Die ersten drei Gaskraftwerke von Entergy wurden im August 2025 genehmigt und sieben weitere liegen bei den Aufsichtsbehörden. Meta geht davon aus, dass die Bauarbeiten bis 2030 andauern werden; Epoch prognostiziert bis zum ersten Quartal 2028 1.632 MW IT-Leistung (eine Epoch-Schätzung).
Die Beobachtungen von Epoch vom 19.04.2026 dokumentieren die verbleibende physische Konstruktion/Installation für dieses benannte Gebäude. Mit „In Bearbeitung“ werden frühere Betriebsgebäude oder zukünftige Kapazitäten nicht fertiggestellt. Leistungs- und Beschleunigerzahlen bleiben Epochenschätzungen und keine vom Betreiber zertifizierte Bewertung. Die modellierten Kapitalkosten in Höhe von 2025 Dollar beinhalten Rechenhardware und sind kein quellennatives Baubudget.
Hyperscale-Frontier-KI-Trainings- und Inferenzcampus, verfolgt von Epoch AI mit kommentierten Satelliten-Footprints (26 physische Teile).
Smalling substation groundbreaking
“Louisiana Public Service Commissioner Foster Campbell speaks during a groundbreaking ceremony for Smalling Substation near Rayville, La., Friday, Jun 27, 2025.”
PSC approves three Entergy gas plants 4-1
“Louisiana Public Service Commissioners voted four to one to approve Entergy's three new gas plants to power Meta's largest-ever data center coming to Northeast Louisiana.”
Foundations underway for main buildings (satellite)
“Foundations are underway for the main buildings, and the overall layout aligns with the architectural renderings published in 2025.”
Deal for seven additional Entergy plants
“Now, as of an announcement on Friday, Meta has a new deal with Entergy, to build and finance seven additional new power plants in Louisiana, Fortune reported.”
PSC votes to expedite seven-plant application
“The Louisiana Public Service Commission voted Wednesday (April 15) to expedite the application for seven new natural gas power plants that would power a second new Meta data center in Richland Parish”
Building 1 and 2 roofs finished, cooling advanced (satellite)
“Building 1 and 2 roof is finished and cooling is at an advanced stage of installation.”
Meta announces additional $40 billion for campus
“Meta has announced that an additional $40 billion will be used to fund the construction of its enormous 4,000 acre data center campus in Richland Parish, Louisiana.”
New power stations in service for 1.8 GW load (Epoch projection)
“New power stations are in service for a 1.8 GW load at Holly Ridge.”
First phase operational (Epoch projection)
“First phase is operational, based on a Meta blog post”
Meta expects construction to continue through 2030
“Meta expects construction to continue through 2030 with site work beginning in December.”