Stated as done, per babcock.com: "(AKRON, Ohio - March 4, 2026) - Babcock & Wilcox ... announced today that it has received full notice to proceed on a $2.4 billion design-build agreement"; the Business Wire copy on Yahoo Finance is timestamped 11:30 UTC.
B&W's filed August 2026 presentation: the $2.4B, 1.2 GW Base Electron project "will be located near Center, North Dakota" and its Conditional Use Permit was submitted in August 2026, with potential for another 1.2 GW.[1]
The agreement itself, dated 26 February 2026: Base Electron is developing a 1,200 MW generation facility; B&W commits to keep the Contract Price within $2,400,000,000 and guarantees each unit's Commercial Operation Readiness date (the schedule is redacted).[1]
Applied Digital's 10-Q: the 4 November 2025 B&W warrant agreement, the 26 February 2026 Design-Build Agreement between Base Electron and B&W, Applied Digital's guarantee of Base Electron's obligations and its ~10% stake in Base Electron.[1]
Industrial Info tracks Applied Digital campuses in Louisiana, Iowa and the Dakotas and links a North Dakota data center with the B&W power system; it names Polaris Forge 1 at Ellendale, not the site B&W later named near Center.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.