A target year, per bismarcktribune.com: Base Electron's Tyler Hammond said that if the permit is approved "construction would commence in the second quarter of 2027 and the plant would be operational in 2030"; a year alone is dated to its last day.
B&W's filed August 2026 presentation: the $2.4B, 1.2 GW Base Electron project "will be located near Center, North Dakota" and its Conditional Use Permit was submitted in August 2026, with potential for another 1.2 GW.[1]
B&W's 10 August 2026 call: Base Electron has submitted its conditional use permit application, most on-site civil and mechanical construction starts in the first part of 2027, and B&W secured reservation rights for 20 50 MW Siemens Energy steam turbines, first sets delivered within 12-14 months, for a second data-centre project.[1]
B&W's Q2 2026 results: the Base Electron project is "progressing ahead of expectations and on budget", boilers and steam turbines are being manufactured, permitting is underway, and it contributed $100.7 million of Q2 revenue.[1]
B&W's 8 January 2026 release: the Siemens Energy turbine sets "will enable B&W to deliver power for the project by the end of 2028" - the date first promised for the plant.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.