Public infrastructure: urban park · Geprüft am 2026-11-06
Nur die gemeldete Phase ist hervorgehoben. Angaben und Termine unterscheiden geplante und nachgewiesene Zustände.
USD 60 million stated park construction budget; primarily funded by the 2018 Parks and Water Bond Act.
“the $60 million Sixth Street PARC”
12 acres of planned open and recreational space below and beside the Sixth Street Viaduct.
“create 12 acres of open and recreational space”
Early 2027 planned opening following playground-equipment installation delays; no exact day published.
“won’t open until early 2027”
Bureau of Engineering began construction in fall 2023; facility still awaiting opening in September 2026 reporting.
“In Fall of 2023”
Construction began
“In Fall of 2023”
Opening delay reported
“scheduling changes to the installation of playground equipment”
Planned opening
“won’t open until early 2027”
We definitely don't want a MacArthur Park duplication. We foresee that happening,
Keeping this park safe requires clear accountability, consistent maintenance, regular programming, and a coordinated response when concerns arise.
Ensuring its success from day one requires the honest dialogue and difficult decisions needed to address legitimate safety and access concerns while recognizing that there is no one-size-fits-all solution
I hope that we can work together and join forces and create a safe space for families to come and enjoy it because it’s an absolutely beautiful park.
Fotos von Lesern, getrennt von den belegten Medien des Pins. Bewerte, was du gegessen oder gesehen hast, und markiere bei einem Restaurant-Pin die Gerichte direkt auf deinem Foto.
Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
The LA Local (16. September 2026): Der Park „wird erst Anfang 2027 eröffnen, Monate später als von der Stadt erwartet“, ein konkretes Datum wurde nicht genannt; Anfang 2027 wird als Ende März angesetzt.
Bureau of Engineering: construction of the $60 million project began in fall 2023; 12 acres of open space under and beside the viaduct; the Leonard Hill Arts Plaza; funded mainly by the 2018 Parks and Water Bond Act; to be completed in 2026.[1]
Bureau of Engineering: the PARC is scheduled to be completed in 2026 and will include soccer fields, trees and paths, the arts plaza, an amphitheater, restrooms, a dog park, skate elements and courts.[1]
LAist's copy of the Boyle Heights Beat story: the 12-acre park won't open until early 2027 because of playground-equipment scheduling changes, per Bureau of Engineering spokesperson Mary Nemick.
Photographed on January 17, 2026: construction nearly complete, especially east of the river, and expected to finish in 2026.[1]
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
Originaltitel: The Park Under the Sixth Street Bridge Opens
Die veröffentlichten Kosten belaufen sich auf 60 Millionen US-Dollar: Angaben des City Bureau of Engineering für das Sixth Street PARC; Einige Pressevertreter geben 82 Millionen US-Dollar an (Quellenkonflikt, nicht offengelegt).[2]
Planned design figure · 12 acres of planned open and recreational space; 12 acres of park space (about 7 acres east side, 5 acres Arts District side).