Der erste Eintrag ist immer die Quelle des Pins. Die Gesamtsicherheit ist ein gewichteter Durchschnitt, wie fest jeder Beleg die oben verwendeten Start- und Endzeiten stützt; ein Beleg zählt für je 180 Tage, die er älter ist als der neueste, nur halb so viel.
Documented physical milestone or dated progress/reporting marker. Period-end dates represent only the reported month/quarter; they do not invent an exact operation date. Source estimates are labelled and not treated as confirmed future opening dates.
Published project-specific cost for Darlington New Nuclear Project — Unit 1: CAD 7.7e+09. Basis: Unit 1 plus shared infrastructure; includes interest, escalation and contingency.[1]
Published electric generating project rating for Darlington New Nuclear Project — Unit 1: 300 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Operator confirms 300 MWe per unit and summer-2026 reactor-building construction after basemat installation.[1]
Fehlt etwas oder stimmt etwas nicht? Sag es in deinen eigenen Worten: ein Link, der diesen Pin belegt, ein anderes Start- oder Enddatum und warum, oder eine Angabe, die fehlt oder falsch ist. Die KI prüft es an den Quellen dieses Pins, sucht nach besseren und ergänzt jede Seite, die dich bestätigt. Die eigenen Quellen des Pins zählen weiterhin am meisten. Auch Bilder sieht sich die KI an: Eines, das etwas anderes oder die Sache schlecht zeigt, wird nach hinten gestellt oder ersetzt.
OPG publishes a C$7.7 billion release-quality budget for the first SMR and shared site infrastructure: C$6.1 billion Unit 1 plus C$1.6 billion common systems/services. The budget includes interest, escalation and contingency. Included output is the first 300 MWe reactor under physical construction; the three additional proposed units and their combined C$20.9 billion fleet budget are excluded.[2][3]
Published project-specific cost for Darlington New Nuclear Project — Unit 1: CAD 7.7e+09. Basis: Unit 1 plus shared infrastructure; includes interest, escalation and contingency.[2]
Published electric generating project rating for Darlington New Nuclear Project — Unit 1: 300 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Operator confirms 300 MWe per unit and summer-2026 reactor-building construction after basemat installation.[3]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.