Energy: battery storage · Verificado el 2026-10-30
Solo se destaca la etapa comunicada. Las cifras y fechas distinguen lo previsto de lo demostrado.
500 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Stein - Rapson 345 kV line","summerNetMW":500.0”
2025-04-01; requested date only, not an achieved opening.
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Stein - Rapson 345 kV line.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
Este pin sigue las noticias: muestra lo que se sabe ahora, y aquí está qué cambió y qué lo provocó.
Editadopor @ThePinGang
ITC Michigan and MISO have advanced system stability and generator interconnection engineering for the 500M USD, 500 MW / 2,000 MWh Stein-Rapson Clean Energy Storage Center in Huron County, Michigan.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date.
ITC Michigan progressed MISO DPP Definitive Planning Study Queue J2140 engineering for the facility. Features 500 MW / 2,000 MWh of utility-grade containerized lithium iron phosphate battery storage. Represents an estimated 500 million USD private clean energy development in Michigan's Thumb region. Interconnects to ITC Michigan's 345 kV Stein to Rapson transmission line. Captures high-volume Thumb wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date. The point of interconnection is Stein - Rapson 345 kV line. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Editadopor @ThePinGang
… wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.
Fotos de lectores, separadas de los medios con fuentes del pin. Valora lo que comiste o viste y, en un pin de restaurante, etiqueta los platos directamente en tu foto.
La primera entrada es siempre la fuente del pin. La confianza global es una media ponderada de la firmeza con la que cada referencia respalda las horas de inicio y fin usadas arriba; una referencia cuenta la mitad por cada 180 días que sea más antigua que la más reciente.
2025-04-01 es la fecha de entrada en servicio solicitada del registro de interconexión, no un día verificado de apertura o operación comercial.
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Título original: Stein-Rapson: 500 MW Battery Interconnection Request J2590
Power storage500 MW · J2590: 500 MW requested battery storage. Queue status: Active. Requested date: 2025-04-01. Not current measured generation; No annual energy or battery MWh inferred. · source