| Date | Observed status |
|---|---|
| 2023-01-01 | Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after. |
| 2025-01-01 | The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. |
| 2025-03-01 | Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but |
| 2025-11-01 | Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. |
| 2026-01-24 | Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have s |
| 2026-06-01 | Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining. |
| 2026-08-06 | On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in |
| 2026-11-01 | Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. |
| 2026-12-31 | Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is abou |
| 2027-12-01 | All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is exclu |
Epoch AI satellite-imagery notes, in date order. · fuente
En construcción
Digital infrastructure: AI data-center campus buildout · Verificado el 2026-10-30
Solo se destaca la etapa comunicada. Las cifras y fechas distinguen lo previsto de lo demostrado.
Epoch’s current campus estimate: 157 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 157 MW”
Physical-stage observation dated 2026-08-06. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“building 9 is under construction”
Epoch’s dated 2026-08-06 assessment: building 9 is under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“building 9 is under construction”
Epoch estimates AI hardware: Huawei Ascend 910C chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Huawei Ascend 910C chips.”
Epoch dated observation: Land clearing begins, with the east campus being the first of the three.
“Land clearing begins, with the east campus being the first of the three.”
Epoch dated observation: On the north campus, building 5 is structurally complete but not…
“On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars.”
Fotos de lectores, separadas de los medios con fuentes del pin. Valora lo que comiste o viste y, en un pin de restaurante, etiqueta los platos directamente en tu foto.
La primera entrada es siempre la fuente del pin. La confianza global es una media ponderada de la firmeza con la que cada referencia respalda las horas de inicio y fin usadas arriba; una referencia cuenta la mitad por cada 180 días que sea más antigua que la más reciente.
La fecha guardada es un marcador de seguimiento estimado o de trayectoria de capacidad, no un día de apertura exacto verificado. El estado de la construcción sigue el alcance físico fechado citado; no se infiere ninguna finalización de los objetivos transcurridos.
Construction research 2026-10-24: Epoch’s[1] 2026-08-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “building 9 is under construction” Dated observation 2026-08-06; future trajectory rows and modeled costs are distinguished from this physical milestone.
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Título original: Huawei Wuhu AI Data Center Buildout
Huawei Wuhu en Wuhu, Anhui, China, es un campus de centro de datos de IA de vanguardia operado por Huawei que alcanza 457 MW de capacidad de energía y 221,924 aceleradores de IA equivalentes a H100. 0
La observación de Epoch del 6 de agosto de 2026 documenta la construcción/instalación física restante para esta construcción nombrada. In Progress no completa edificios operativos anteriores ni capacidad futura. Los recuentos de potencia y acelerador siguen siendo estimaciones de Epoch, no una clasificación certificada por el operador. Los costos de capital modelados en dólares de 2025 incluyen hardware informático y no son un presupuesto de construcción original.