Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fuente
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fuente
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fuente
| Date | Observed status |
|---|---|
| 2024-11-01 | Land clearing begins. |
| 2026-02-14 | Buildings 1 and 2 under construction. Building 1's chillers are almost all in place, while only half of Building 2's are. Optimus substation, which is the substation on site, and the expansion of Dowl |
| 2026-07-30 | Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the [Apollo Pow |
| 2027-02-01 | Building 1 is operational, based on a 5 month extrapolation from its roof completion date. |
| 2027-04-01 | Building 2 is operational, based on construction progress as of Sep 2026 and foundations being laid around 2 months after Building 1. |
| 2028-01-01 | Buildings 3 and 4 are operational, based on their construction starting 11 months after Building 1. We assume they are powered by the 350 MW Apollo Power Generation Project. |
Epoch AI satellite-imagery notes, in date order. · fuente
En construcción
Digital infrastructure: AI data-center campus buildout · Verificado el 2026-10-30
Solo se destaca la etapa comunicada. Las cifras y fechas distinguen lo previsto de lo demostrado.
Epoch’s current campus estimate: 0 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 0 MW”
Physical-stage observation dated 2026-07-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Construction on Buildings 3 and 4 has begun”
Epoch’s dated 2026-07-30 assessment: Construction on Buildings 3 and 4 has begun Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Construction on Buildings 3 and 4 has begun”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch dated observation: Roofs of Buildings 1 and 2 are more than halfway complete.
“Roofs of Buildings 1 and 2 are more than halfway complete.”
Fotos de lectores, separadas de los medios con fuentes del pin. Valora lo que comiste o viste y, en un pin de restaurante, etiqueta los platos directamente en tu foto.
La primera entrada es siempre la fuente del pin. La confianza global es una media ponderada de la firmeza con la que cada referencia respalda las horas de inicio y fin usadas arriba; una referencia cuenta la mitad por cada 180 días que sea más antigua que la más reciente.
La fecha guardada es un marcador de seguimiento estimado o de trayectoria de capacidad, no un día de apertura exacto verificado. El estado de la construcción sigue el alcance físico fechado citado; no se infiere ninguna finalización de los objetivos transcurridos.
Construction research 2026-10-24: Epoch’s[1] 2026-07-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Construction on Buildings 3 and 4 has begun” Dated observation 2026-07-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Título original: Meta Bowling Green AI Data Center Buildout
Meta Bowling Green en Bowling Green, Ohio, Estados Unidos, es un campus de centro de datos de IA de vanguardia operado por Meta que alcanza 422 MW de capacidad de energía y 855,159 aceleradores de IA equivalentes a H100. 0
La observación de Epoch del 30 de julio de 2026 documenta la construcción/instalación física restante para esta construcción nombrada. In Progress no completa edificios operativos anteriores ni capacidad futura. Los recuentos de potencia y acelerador siguen siendo estimaciones de Epoch, no una clasificación certificada por el operador. Los costos de capital modelados en dólares de 2025 incluyen hardware informático y no son un presupuesto de construcción original.