Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fuente
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fuente
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · fuente
| Date | Observed status |
|---|---|
| 2024-05-31 | Land clearing begins for northern two buildings (Building 1-2) |
| 2025-06-28 | Building 1 looks close to finishing construction, with chillers in place. OpenAI [stated](https://openai.com/index/five-new-stargate-sites/) that "Oracle began delivering the first NVIDIA GB200 racks |
| 2025-09-26 | Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe [announcement](https://www.crusoe.ai/resources/newsroom/crusoe-announces-flagship-abilen |
| 2025-12-24 | Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a [TDLR filing](https:// |
| 2026-01-15 | The 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation i |
| 2026-03-24 | Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according t |
| 2026-05-23 | Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle [posted](https://x.com/i/status/2047012589302153558) that "In Abilene, 200MW is already operational". This suggests that there |
| 2026-07-28 | Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete. |
| 2026-09-10 | Buildings 5-6 are operational. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now be |
| 2026-11-01 | Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This n |
Epoch AI satellite-imagery notes, in date order. · fuente
En construcción
Data center · Verificado el 2026-10-31
Solo se destaca la etapa comunicada. Las cifras y fechas distinguen lo previsto de lo demostrado.
$15 billion
“announced the second phase of a $15 billion joint venture to fund the campus.”
About 4 million sq ft, eight buildings
“bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
875 acres
“sits Stargate — an 875-acre AI data center campus”
618 MW delivered of 824 MW IT projected (Epoch); campus 1.2 GW grid-level design
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Six of eight buildings delivered; Buildings 7-8 fit-out
“Buildings 5-6 are operational.”
Land clearing begins for Buildings 1-2 (Epoch satellite observation)
“Land clearing begins for northern two buildings (Building 1-2)”
City council approves 85%, 10-year tax abatements
“The Abilene City Council approved 85 percent, 10-year property tax abatements for the site in February 2025”
Second phase of six more buildings announced (eight total, 1.2 GW)
We got taken, we got robbed,
So were there things we could have done different? Of course there were,
Who exactly is paying for all of this?
come to Abilene every day to build the future of AI infrastructure
| Crusoe tops off final AI data center in Abilene (w.media): Crusoe on its workforce · 18 nov 2025 | 0.80 |
|---|---|
| Abilene Is Paying The Price For Texas' Billionaire Giveaways (Lone Star Left, opinion) · 21 abr 2026 | -0.80 |
| Officials say data centers can boost local economies. In Abilene, they have spurred a housing crisis (KUT/TPR): resident Lexi Smith · 12 ago 2026 | -0.90 |
| AI Next Door: What Abilene learned living by Stargate (WTOC): Mayor Weldon Hurt · 26 oct 2026 | -0.20 |
Fotos de lectores, separadas de los medios con fuentes del pin. Valora lo que comiste o viste y, en un pin de restaurante, etiqueta los platos directamente en tu foto.
La primera entrada es siempre la fuente del pin. La confianza global es una media ponderada de la firmeza con la que cada referencia respalda las horas de inicio y fin usadas arriba; una referencia cuenta la mitad por cada 180 días que sea más antigua que la más reciente.
El comienzo es el desmonte de tierras observado por satélite de Epoch[3][7]; Crusoe dice que la construcción comenzó en junio de 2024. El final es la operación estimada de Epoch para noviembre de 2026 de los Edificios 7-8; no se publica ninguna fecha del desarrollador.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][7] 2026-07-28 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “not yet confirmed operational” Dated observation 2026-07-28; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Título original: OpenAI Stargate Abilene AI Data Center Buildout
El campus Stargate de OpenAI en Abilene, Texas, es el desarrollo de ocho edificios de Crusoe, de aproximadamente 4 millones de pies cuadrados y 1,2 GW, arrendado a Oracle. La construcción comenzó en 2024; Oracle informó que seis de los ocho edificios se entregaron el 10 de septiembre de 2026, y los dos últimos aún se están acondicionando. Una empresa conjunta de 15.000 millones de dólares financia el campus. Epoch AI estima 618 MW de potencia de TI ahora y 824 MW cuando esté completo.
La observación de Epoch del 28 de julio de 2026 documenta la construcción/instalación física restante para esta construcción nombrada. In Progress no completa edificios operativos anteriores ni capacidad futura. Los recuentos de potencia y acelerador siguen siendo estimaciones de Epoch, no una clasificación certificada por el operador. Los costos de capital modelados en dólares de 2025 incluyen hardware informático y no son un presupuesto de construcción original.
Campus de inferencia y entrenamiento de IA de frontera a hiperescala rastreado por Epoch AI con huellas satelitales anotadas (70 partes físicas).
“announced a second phase of six more buildings, bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
$15 billion Crusoe/Blue Owl/Primary Digital joint venture announced for the campus
“On May 21, 2025, Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced the second phase of a $15 billion joint venture to fund the campus.”
Buildings 1-2 live on Oracle Cloud Infrastructure
“Crusoe said on Sept. 30, 2025, that the first phase was running on Oracle Cloud Infrastructure”
Crusoe tops out the eighth and final building
“Crusoe has marked a major milestone in its AI infrastructure expansion by topping out the eighth and final building”
Building 2 fully operational (Epoch estimate; matches TDLR completion date)
“Building 2 is fully operational.”
OpenAI and Oracle drop plan to expand Abilene beyond about 1.2 GW
“OpenAI had planned to expand this site to 2.1 GW, but recently reversed course”
Buildings 5-8 structurally complete and roofed; fit-out ongoing
“Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing).”
Oracle: six of eight buildings, 618 MW, delivered
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Buildings 7-8 estimated operational (full campus; Oracle gave no date)
“Buildings 7-8 are estimated to be operational.”