El inicio es el desmonte de terrenos con fecha satelital de Epoch[3] (30 de mayo de 2024); el comunicado del gobierno dice que estará operativo en la primavera de 2027 (precisión de temporada), por lo que endDate es nulo.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1] 2026-04-08 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “there's still some equipment strewn around the site” Dated observation 2026-04-08; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
| 2026-04-08 | Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site. We expect around 3 more months needed for commissioning and server installation. |
|---|
| 2026-08-07 | Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2. |
|---|
| 2026-11-05 | Building 2 is operational assuming a 3 month lag compared to Building 1. |
|---|
Epoch AI satellite-imagery notes, in date order. · fuente
100 operational jobs and 1,000 construction jobs
“will bring 100 operational jobs as well as 1,000 construction jobs”
715,000 sq ft
“the 715,000-square-foot data center, located in the Sage Mill Industrial Park in Aiken County”
300+ acres
“Situated on a 300+ acre site in Aiken County, South Carolina”
69 MW now; 129 MW projected
“supported by 69 MW of IT power”
Building 1 operational; Building 2 commissioning
“Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans.”
Land clearing begins (satellite)
“Land clearing begins”
Meta announces $800 million Aiken County data center
“The $800 million investment will support 100 new operational jobs.”
SELC files FOIA request on projected water use and incentives
“the Southern Environmental Law Center requested documents from Aiken County regarding the anticipated water usage of Meta's proposed data center”
Data center under construction at Sage Mill
“Meta is building one of the massive information storage facilities at the Sage Mill Industrial Park in the Graniteville/Vaucluse area.”
Buildings 1 and 2 nearly complete (satellite)
“Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site.”
Building 1 confirmed operational via drone imagery
“Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans.”
Building 2 operational (Epoch projection)
“Building 2 is operational assuming a 3 month lag compared to Building 1.”
Meta's operational target for the data center
“It is expected to be operational in spring 2027.”
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Título original: Meta Aiken AI Data Center Buildout
El primer centro de datos de Meta en Carolina del Sur es un campus optimizado para IA de 715.000 pies cuadrados y 800 millones de dólares en el Parque Industrial Sage Mill, cerca de Graniteville en el condado de Aiken. La limpieza del terreno comenzó en mayo de 2024, la revisión basada en drones de Epoch confirma que el Edificio 1 estará operativo en agosto de 2026 y el Edificio 2 aún está en funcionamiento, y el objetivo declarado de Meta para el campus es la primavera de 2027.
La observación de Epoch del 2026-04-08 documenta la construcción/instalación física restante para esta construcción nombrada. In Progress no completa edificios operativos anteriores ni capacidad futura. Los recuentos de potencia y acelerador siguen siendo estimaciones de Epoch, no una clasificación certificada por el operador. Los costos de capital modelados en dólares de 2025 incluyen hardware informático y no son un presupuesto de construcción original.
Campus de inferencia y entrenamiento de IA de frontera a hiperescala rastreado por Epoch AI con huellas satelitales anotadas (6 partes físicas).