Construction research 2026-10-24: Epoch’s[1] 2026-04-23 observation documents the identified building scope complete or operating, using physical observations or explicit delivery rather than an elapsed target date. Completed is limited to that scope. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Google’s actual Waltham Cross opening corroborates complete buildout, distinct from the generic 250MW seed value. Source quote: “Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image” Dated observation 2026-04-23; future trajectory rows and modeled costs are distinguished from this physical milestone.
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Physical-stage observation dated 2026-04-23. Named completed buildings only; later expansion is not marked completed. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image”
Epoch’s dated 2026-04-23 assessment: Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image Named completed buildings only; later expansion is not marked completed.
“Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image”
Epoch estimates AI hardware: Google TPU v6e chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v6e chips.”
Epoch dated observation: Land clearing begins (Sentinel-2 imagery).
“Land clearing begins (Sentinel-2 imagery).”
Epoch dated observation: Full buildout reconfirmed via high-resolution Pléiades-Neo satellite…
“Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image; no capacity change since September 2025.”
Título original: Google Waltham Cross AI Data Center — Completed Buildings
La observación de Epoch del 23 de abril de 2026 documenta el alcance del edificio identificado completo u operativo, utilizando observaciones físicas o entrega explícita en lugar de una fecha objetivo transcurrida. Completado se limita a ese alcance. Los recuentos de potencia y acelerador siguen siendo estimaciones de Epoch, no una clasificación certificada por el operador. Los costos de capital modelados en dólares de 2025 incluyen hardware informático y no son un presupuesto de construcción original. La apertura real de Waltham Cross de Google corrobora la construcción completa, distinta del valor inicial genérico de 250 MW.
Campus de inferencia y entrenamiento de IA de frontera a hiperescala rastreado por Epoch AI con huellas satelitales anotadas (5 partes físicas).