La primera entrada es siempre la fuente del pin. La confianza global es una media ponderada de la firmeza con la que cada referencia respalda las horas de inicio y fin usadas arriba; una referencia cuenta la mitad por cada 180 días que sea más antigua que la más reciente.
El desarrollador Nate Cadieux dijo el 19 de marzo de 2026 que la construcción probablemente no comenzaría hasta dentro de 18 a 24 meses, es decir, entre septiembre de 2027 y marzo de 2028; la fecha que se muestra es el inicio de ese período y se desconoce el resultado de la apelación.
Planning Commission 6-0 approval, 16/76 unit split, parking, retail area, address, 18-24 month start estimate.[1]
Context on the appellant's motives and the council's two options.[1]
Regional per-unit cost benchmark ($420k-$615k, vertical hard cost) behind the estimated price; not specific to this project.[1]
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Benchmark for California (Los Angeles, Bay Area, San Diego) wood-frame podium projects.
“California (LA, Bay, San Diego) $420k–$615k/unit Highest US wood-frame cost.”
Top of the same published range.
“California (LA, Bay, San Diego) $420k–$615k/unit Highest US wood-frame cost.”
Low: 92 × $420,000 = $38,640,000. High: 92 × $615,000 = $56,580,000.
92 × $517,500 (midpoint per unit) = $47,610,000, the midpoint ($47,610,000) rounded to $47 million.
Land, design and permit fees, financing and the developer fee. The benchmark is for new wood-frame construction; the structural system and the cost of restoring the historic building are not published, so the real figure could differ. This is an estimate of vertical building cost, not a published budget.
Roughly 4,900 sq ft, plus one level of underground parking with 23 spaces
“It also calls for one level of underground parking with 23 spots, and roughly 4,900 square feet of commercial space on the ground level.”
92 units in a seven-story building: 16 subsidized, 76 market rate
“The new project will include 16 subsidized apartments mixed in with the 76 market-rate units.”
September 2027 to March 2028 (18 to 24 months after March 2026), per the developer; no completion date published
“Cadieux said construction will likely not happen for another 18 to 24 months because of additional planning and permits.”
Approved 6-0 by the Planning Commission on March 19, 2026; environmental appeal to the City Council (hearing June 30, 2026, outcome not reported); construction not started
“On June 30, the San Diego City Council will consider the claims of inadequate environmental review.”
SAFER files environmental appeal
“In its March 31 appeal, SAFER alleges that developer Nathan Cadieux and his firm Purpose”
City Council hearing on the appeal (outcome not found)
“On June 30, the San Diego City Council will consider the claims of inadequate environmental review.”
Estimated construction start
“Cadieux said construction will likely not happen for another 18 to 24 months because of additional planning and permits.”
Título original: Newman Building Redevelopment (North Park)
No se ha publicado ningún presupuesto de construcción, por lo que el precio del pin es una estimación construida a partir de estas piezas:
Las imágenes principales son representaciones del edificio propuesto, publicadas con la cobertura de la Comisión de Planificación; la tercera foto muestra el edificio actual.