Second Avenue Subway Phase 2 Opens
- Phase 2 of the Second Avenue Subway extends the Q 1.5 miles from 96th Street to 125th Street in East Harlem, with new stations at 106th, 116th and 125th Streets; construction began June 2026[1][2]
- Cost was reported at $6 billion by Wikipedia and $6.99 billion by amNewYork, which said it was "slated to open in September 2032"[1][3]
- Contract 2 ($1.97 billion, Connect Plus Partners) covers tunnelling from 116th to 125th Street; Contract 3 went to the Skanska-Walsh-Traylor JV for 106th Street in June 2026; tunnel boring from 120th Street begins 2027[2][3]
- A November 2023 full funding grant agreement provides $3.4 billion in federal funding[2]
- Phase 1 opened January 1, 2017 (72nd, 86th, 96th Streets, $4.45 billion); the line was first proposed in 1920; the full 10-mile line is projected at more than $24.7 billion[1]
- Phases 1 and 2 together are expected to carry about 300,000 riders a day; Phase 2 alone about 110,000[2][3]
References 369% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]50%en.wikipedia.org/wiki/Second_Avenue_Subwayen.wikipedia.org· Posted Sep 11, 2026· Starts Dec 1, 2032 ✓· 45% of score
Given as a target, not a fixed date, per the pin description: "…tury after the line was first proposed. Estimated date.…"
- [2]85%Second Avenue Subway Phase 2mta.info· Added Sep 14, 2026· 45% of score
The MTA's own project page is the authoritative primary source for Second Avenue Subway Phase 2's status, consistent with the pin's "estimated date" framing, though a 403 error blocked retrieval of its text to quote a specific date.
- [3]78%MTA to approve $1.97 billion tunneling contract to push Second Avenue subway into East Harlemamny.com· Published Aug 15, 2025· 10% of score
amNewYork reports the project is "slated to open in September 2032," corroborating the pin's stored estimated December 2032 date to within the same year, while noting the tunnel boring machine wasn't even expected until 2027.[1]
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.