5 hectares
“Situated in a 5-hectare property in Sta. Rosa, Laguna, the 50 MW capacity VITRO Sta Rosa (VSR) is on target to go live this coming July”
50 MW
“The company has commissioned a 115-kilovolt switching station that will help the data center meet its 50-megawatt (MW) power demand”
March 2022 to April 2025
“has inaugurated the first VITRO hyperscale data center in Sta. Rosa, Laguna”
Inaugurated 23 April 2025
“has inaugurated the first VITRO hyperscale data center in Sta. Rosa, Laguna”
Groundbreaking ceremony
“The groundbreaking ceremony took place in Sta. Rosa, Laguna where the VITRO Sta. Rosa Data Center by PLDT will rise in 2023.”
Meralco 115-kV switching station commissioned
“The company has commissioned a 115-kilovolt switching station that will help the data center meet its 50-megawatt (MW) power demand”
We do intend to expand our data center capacity to up to 500 megawatts (MW)
The switching station design incorporates redundancy features, which guarantees our customer's data center can maintain uninterrupted services
This facility is prepared to host and manage the Philippines' most robust computing infrastructure, supporting generative AI, large language models, and other high-performance workloads.
| Meralco's new facility to power PLDT's Laguna data center · 5 nov 2024 | 0.70 |
|---|---|
| VITRO Sta. Rosa data center now AI-ready after energization · 10 nov 2024 | 0.80 |
| PLDT launches Sta. Rosa data center, finalizes 12th site in Cavite · 23 abr 2025 | 0.80 |
Fotos de lectores, separadas de los medios con fuentes del pin. Valora lo que comiste o viste y, en un pin de restaurante, etiqueta los platos directamente en tu foto.
La primera entrada es siempre la fuente del pin. La confianza global es una media ponderada de la firmeza con la que cada referencia respalda las horas de inicio y fin usadas arriba; una referencia cuenta la mitad por cada 180 días que sea más antigua que la más reciente.
La fecha pin 2025-04-23 es la inauguración (demostrada). La pieza de Rappler[10] tiene fecha del 22 de marzo de 2022, pero no indica el día de la ceremonia, por lo que la fecha de inicio es esa fecha de publicación, no una fecha de ceremonia confirmada.
PLDT's[1] 20-F calls the launch of VITRO Santa Rosa a key 2025 milestone and says it hosts ePLDT's Pilipinas AI platform for enterprise and hyperscaler customers.
Philippine News Agency report of Marcos leading the grand launch on Wednesday, 23 April 2025, of the 50 MW VSR, linked to subsea cables to Asia, the US and Europe.[1]
BusinessWorld: five-hectare campus of up to 50 MW, NVIDIA-powered GPU servers, VITRO's 11 sites totalling nearly 100 MW, and a planned 100 MW 12th site in General Trias, Cavite.[1]
Daily Tribune on the inauguration with Marcos and Trade Secretary Cristina Roque, and ePLDT's GPU-as-a-Service offering.
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
Título original: VITRO Sta. Rosa, the Philippines' First AI-Ready Hyperscale Data Center, Opens
Facility energized, ready for client equipment
“has completed the energization of its VITRO Sta. Rosa (VSR) data center”
20 MW of IT power targeted by end of 2024
“will deliver 20 Megawatts of IT power by year's end, with 35 percent coming from renewable energy”
Inauguration of VITRO Sta. Rosa
“has inaugurated the first VITRO hyperscale data center in Sta. Rosa, Laguna”