La primera entrada es siempre la fuente del pin. La confianza global es una media ponderada de la firmeza con la que cada referencia respalda las horas de inicio y fin usadas arriba; una referencia cuenta la mitad por cada 180 días que sea más antigua que la más reciente.
Documented physical milestone or dated progress/reporting marker. Period-end dates represent only the reported month/quarter; they do not invent an exact operation date. Source estimates are labelled and not treated as confirmed future opening dates.
Published project-specific cost for Darlington New Nuclear Project — Unit 1: CAD 7.7e+09. Basis: Unit 1 plus shared infrastructure; includes interest, escalation and contingency.[1]
Published electric generating project rating for Darlington New Nuclear Project — Unit 1: 300 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Operator confirms 300 MWe per unit and summer-2026 reactor-building construction after basemat installation.[1]
¿Falta algo o hay un error? Dilo con tus palabras: un enlace que respalde este pin, otra fecha de inicio o fin y por qué, o un dato que falta o está mal. La IA lo contrasta con las fuentes del pin, busca otras mejores y añade cualquier página que te dé la razón. Las fuentes del propio pin siguen contando más. La IA también mira las imágenes: una que muestra otra cosa, o la muestra mal, pasa al final o se sustituye.
OPG publishes a C$7.7 billion release-quality budget for the first SMR and shared site infrastructure: C$6.1 billion Unit 1 plus C$1.6 billion common systems/services. The budget includes interest, escalation and contingency. Included output is the first 300 MWe reactor under physical construction; the three additional proposed units and their combined C$20.9 billion fleet budget are excluded.[2][3]
Published project-specific cost for Darlington New Nuclear Project — Unit 1: CAD 7.7e+09. Basis: Unit 1 plus shared infrastructure; includes interest, escalation and contingency.[2]
Published electric generating project rating for Darlington New Nuclear Project — Unit 1: 300 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Operator confirms 300 MWe per unit and summer-2026 reactor-building construction after basemat installation.[3]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.