Energy: battery storage · Vérifié le 2026-10-30
Seule l’étape rapportée est mise en évidence. Les chiffres et dates distinguent les projets des faits démontrés.
205 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Hazleton","summerNetMW":205.0”
2028-06-30; requested date only, not an achieved opening.
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00","inService":"2028-06-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; Hazleton.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00","inService":"2028-06-30T04:00:00+00:00"”
Ce pin suit l'actualité : il montre ce que l'on sait maintenant, et voici ce qui a changé et pourquoi.
Modifiépar @ThePinGang
Alliant Energy / Interstate Power and Light development of the Hazleton Clean Energy Storage Center in Buchanan County, Iowa. TheJ3780 is a 205 MW / 820 MWh battery facility connects to the 345 kV Hazleton substation hub, providing essential grid flexibility, wind generation firming, and local transmission support across northeastern Iowa.battery storage interconnection request in Buchanan, IA. The grid operator lists its queue status as Active. The requested in-service date is 2028-06-30; this is a planning date.
Alliant Energy / Interstate Power and Light advanced engineering reviews for the Hazleton Clean Energy Storage Center. Features 205 MW / 820 MWh of grid-scale battery storage capacity in Buchanan County, Iowa. RepresentsJ3780 is a 205 MW battery storage interconnection request in Buchanan, IA. The grid operator lists its queue status as Active. The requested in-service date is 2028-06-30; this is a 220 million USD private clean energy infrastructure investment in eastern Iowa. Connects to the 345 kV Hazleton substation hub within the MISO transmission footprint. Enhances grid flexibility, firms regional wind generation, and reinforces transmission reliability. Timeline: planned project targeting commercial operation in June 2028 (estimated) under MISO interconnection queue and state regulatory schedules.planning date. The point of interconnection is Hazleton. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
Modifiépar @ThePinGang
… firms regional wind generation, and reinforces transmission reliability. Timeline: planned project targeting commercial operation in June 2028 (estimated) under MISO interconnection queue and state regulatory schedules.
Modifiépar @ThePinGang
Photos de lecteurs, distinctes des médias sourcés du pin. Notez ce que vous avez mangé ou vu et, sur un pin de restaurant, identifiez les plats directement sur votre photo.
La première entrée est toujours la source de l’épingle. La confiance globale est une moyenne pondérée de la fermeté avec laquelle chaque référence étaye les heures de début et de fin retenues ci-dessus ; une référence compte moitié moins pour chaque tranche de 180 jours d’ancienneté par rapport à la plus récente.
Il manque quelque chose ou une erreur s'est glissée ? Dites-le avec vos mots : un lien qui étaye cette épingle, une autre date de début ou de fin et pourquoi, ou une information absente ou erronée. L'IA la vérifie au regard des sources de l'épingle, en cherche de meilleures et ajoute toute page qui vous donne raison. Les sources de l'épingle restent celles qui comptent le plus. L'IA regarde aussi les images : une image qui montre autre chose, ou qui le montre mal, passe en dernier ou est remplacée.
Titre original: Hazleton: 205 MW Battery Interconnection Request J3780
Power storage205 MW · J3780: 205 MW requested battery storage. Queue status: Active. Requested date: 2028-06-30. Not current measured generation; No annual energy or battery MWh inferred. · source