Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · source
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · source
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · source
| Date | Observed status |
|---|---|
| 2024-04-20 | Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete. |
| 2024-09-13 | Building 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Buildi |
| 2025-06-01 | Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on |
| 2025-10-14 | Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in p |
| 2026-01-18 | Water vapor from cooling towers is present across Building 1-4, confirming their operation. Building 5 roof is still incomplete, but most backup generators and 5 cooling towers have been installed. |
| 2026-03-12 | Building 5 has more cooling towers installed but not complete, and the roof is almost complete. |
| 2026-05-18 | Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational. |
Epoch AI satellite-imagery notes, in date order. · source
En construction
Digital infrastructure: AI data-center campus buildout · Vérifié le 2026-10-30
Seule l’étape rapportée est mise en évidence. Les chiffres et dates distinguent les projets des faits démontrés.
Epoch’s current campus estimate: 333 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 333 MW”
Physical-stage observation dated 2026-05-18. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“there is still light work around the building”
Epoch’s dated 2026-05-18 assessment: there is still light work around the building Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“there is still light work around the building”
Epoch estimates AI hardware: Google TPU v5e, Google TPU v5p, and Google TPU v6e chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v5e, Google TPU v5p, and Google TPU v6e chips.”
Epoch dated observation: Building 1 is operational.
“Building 1 is operational.”
Epoch dated observation: Building 5 has all cooling towers installed, and all other components…
“Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building.”
Photos de lecteurs, distinctes des médias sourcés du pin. Notez ce que vous avez mangé ou vu et, sur un pin de restaurant, identifiez les plats directement sur votre photo.
La première entrée est toujours la source de l’épingle. La confiance globale est une moyenne pondérée de la fermeté avec laquelle chaque référence étaye les heures de début et de fin retenues ci-dessus ; une référence compte moitié moins pour chaque tranche de 180 jours d’ancienneté par rapport à la plus récente.
La date enregistrée est un marqueur de suivi ou de trajectoire de capacité estimé, et non un jour d'ouverture exact vérifié. L'état de la construction suit la portée physique datée citée ; aucun achèvement n’est déduit des objectifs écoulés.
Construction research 2026-10-24: Epoch’s[1] 2026-05-18 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “there is still light work around the building” Dated observation 2026-05-18; future trajectory rows and modeled costs are distinguished from this physical milestone.
Il manque quelque chose ou une erreur s'est glissée ? Dites-le avec vos mots : un lien qui étaye cette épingle, une autre date de début ou de fin et pourquoi, ou une information absente ou erronée. L'IA la vérifie au regard des sources de l'épingle, en cherche de meilleures et ajoute toute page qui vous donne raison. Les sources de l'épingle restent celles qui comptent le plus. L'IA regarde aussi les images : une image qui montre autre chose, ou qui le montre mal, passe en dernier ou est remplacée.
Titre original: Google New Albany AI Data Center Buildout
Google New Albany à New Albany, Ohio, États-Unis est un campus de centre de données d'IA frontalier exploité par Google / Google DeepMind atteignant 333 MW de capacité électrique et 323 901 accélérateurs d'IA équivalents H100. 0
L’observation d’Epoch du 18/05/2026 documente la construction/installation physique restante pour cette construction nommée. In Progress ne complète pas les bâtiments opérationnels antérieurs ni la capacité future. Les décomptes de puissance et d’accélérateur restent des estimations d’époque, et non une évaluation certifiée par l’opérateur. Les coûts d’investissement modélisés en dollars 2025 incluent le matériel informatique et ne constituent pas un budget de construction natif.